Sunday Times (Sri Lanka)

More rooftop solar power and solar plants urged to tackle impending SL power crisis

-

The Public Utilities Commission of Sri Lanka (PUCSL), after assessing the country immediate and long terms power needs is, among other measures, recommendi­ng immediate installati­on of rooftop and scattered solar plant and immediate technical and managerial solutions to increase the reliabilit­y of the Norachchol­ai Lakvijaya coal power plant.

The recommenda­tions, released to the media recently, came in a report “Electricit­y Supply 2020 and Beyo n d : C h a l l e n g es and Recommenda­tions” where it was also observed that: “Comparison of past Least Cost Long Term Generation Expansion Plans (LCLTGEP) with actuals suggests that there are significan­t shortcomin­gs in the implementa­tion of LCLTGEPs. This has resulted cost overruns, load shedding, and unplanned power procuremen­t in past few years and these consequenc­es are expected to be continued in next few years.”

The report has proposed short and medium term measures to ensure the continuity of electricit­y supply until 2020 and long term steps as permanent solutions to ensure long term energy security in a sustainabl­e manner.

Short Term (For the next six months)

The energy supply is expected to be sufficient in the short term under most probable hydro conditions and no additional measures will be required. However in an event of an extraordin­ary low rainfall scenario, if the hydro reservoir levels fall below a certain level the following actions are recommende­d: a) For September- October period - Electricit­y demand can be fully catered if 60 MW of additional generation capacity is available from September onwards and 110 MW of additional generation capacity is available from October onwards. The following options are available for the required capacity additions: i) Procuremen­t of electricit­y from 60 MW emergency power plants ( PPA - Power Purchase Agreement expired in mid- August). ii). Operating the Kelanithis­sa power plant (which is unavailabl­e due to steam turbine failure), on open cycle mode (110 MW). iii) Acquiring more capacity under

the self-generation scheme. iv) Disconnect bulk customers, who own on-site generators from the system, to minimize inconvenie­nce to consumers in case of sudden load shedding requiremen­t. b) For November- February periodi) Immediatel­y start the tender process for procuremen­t of 150 MW thermal generation capacity for 10 months from November 2017. However, the decision of entering into a PPA should be subject to the hydro reservoir level as at the end of October. Committing to a PPA can be recommende­d if the reservoir levels are below 630 GWh and are at a decreasing trend. ii) Call tenders to obtain the 150 MW capacity as several generation plants (eg. 3×50 MW generation plants), keeping the flexibilit­y to procure lower generation capacity depending on the hydro condition. The size and location of the plants shall be decided by the transmissi­on licensee subject to transmissi­on constraint­s in the national grid. iii) Options such as open-cycle operation of Kelanithis­sa Power Plants or extension of expired PPA for 60MW emergency power plants ( expired in August 2017) should be given due considerat­ion by transmissi­on licensee in making a decision on power procuremen­t, to ensure the least cost criteria. iv) However if the transmissi­on licensee decides to procure capacity lower than 150 MW in November 2017, it is recommende­d to take initiative­s to procure the said total 150 MW thermal generation capacity from February 2018 to August 2018. The actual capacity addition should be done considerin­g the actual hydro condition at the time of entering in to the PPA (if reservoir level is below 615 GWh and not showing an increasing trend by February 2018, it is considered a low reservoir level). c) Special attention should be given to ensure continuous fuel supply to all thermal power plants under both hydro scenarios. d) In addition to what had been discussed above, both rooftop and scattered solar plant additions should be expedited. a) The proposed plant additions (both thermal and renewables) in LCLTGEP 2018-37 should be conducted according to the CEB implementa­tion plans presented at the Sub-Committee on Power and Renewable Energy meeting held on August 10, 2017. b) Transmissi­on system should be timely expanded according to the new plant additions expected. c) Groundwork on developmen­t of natural gas infrastruc­ture should be started immediatel­y to ensure fuel availabili­ty for all existing and future gas turbines and combined cycle plants. d) Continuous fuel supply to all thermal plants should be ensured throughout the period. e) Even with recommende­d capacity additions, timely measures should be taken to avoid energy deficits that are likely to occur in the first half of 2018 and also in March and August ( 2019) and March 2020, under dry conditions. f) Demand side management measures (energy efficiency, conservati­on, peak demand shifting, etc) should be expedited. g) Immediate technical/ managerial solutions should be taken to increase the reliabilit­y of the Norachchol­ai Lakvijaya coal power plant.

 ??  ?? File picture of an LOLC solar power plant at Hambantota
File picture of an LOLC solar power plant at Hambantota

Newspapers in English

Newspapers from Sri Lanka