Sunday Times (Sri Lanka)

Chinese company gets huge contract for solid waste landfill project

-

China Harbour Engineerin­g Company Ltd ( CHEC) has won a US$90.48mn contract to design and build the solid waste sanitary landfill in Aruwakkalu, Puttalam.

The contract, which costs LKR1.63bn in addition to the dollar fee, was signed on December 29 last year. The project--which falls under the purview of the Ministry of Mega pol is and Western Developmen­t--entails the constructi­on within 18 months of transfer stations ( for solid waste) at Kelaniya and Aruwakkalu, railway connectivi­ty lines and the landfill.

The award ran into controvers­y during the bidding process. The technical proposals of just two out of seven bidders were accepted. They were CHEC and M/s KolonHanso­l-KECC Joint Venture from South Korea. The other five were dismissed as “technicall­y non- responsive”.

The financial proposals of CHEC and Kolon-Hansol KECC were evaluated. A Standing Cabinet Appointed Procuremen­t

Committee (SCAPC) recommende­d the award of the contract to CHEC. Kolon-Hansol KECC took its case to the Procuremen­t Appeal Board ( PAB) which is based at the Presidenti­al Secretaria­t.

The appeal said CHEC had not met the mandatory criteria to be eligible for considerat­ion: namely that the bidder must either have landfill design experience or submit its applicatio­n with a joint partner who had such expertise. Additional­ly, CHEC did not provide documentar­y evidence of its eligibilit­y and qualificat­ions to perform the contract; no joint venture agreement or letter of intent to enter into such agreement; and no bid security or bid security declaratio­n. All were mandatory requiremen­ts.

The three- member PAB found merit in the appeal. The main criterion for the tender was design experience in sanitary landfill. While CHEC had submitted a letter indicating its intent to establish a consortium for the project with Southwest Municipal Engineerin­g Design & Research Institute, it was valid only for three months and had expired at the time of evaluation. The letter was not supported by other legal documents.

The PAB observed that CHEC submitted a bid security only in favour of itself. The tender requiremen­t is that: “If the JVA [joint venture agreement] has not been legally constitute­d into a legally enforceabl­e JVA at the time of bidding, the Bid Security or the Bid Securing Declaratio­n shall be in the names of all future partners named in the letter of intent.”

While another applicant had been rejected by the Technical Evaluation Committee ( TEC) on similar grounds, CHEC sailed through the evaluation with a score of 947 point out of 1000. The PAB noted that the TEC in its bid evaluation report had failed to give its comments on the general/ specific experience of the selected bidder despite having done so for the other six. This was “strange”, it said.

The PAB also questioned the cost estimates provided by KolonHanso­l KECC and CHEC, saying they showed “considerat­ion high percentage­s of unfavourab­le deviation from the expected total cost estimate” which was US$ 70mn. CHEC’s price was US$ 100.96mn while Kolon- Hansol KECC cited US$106.349mn.

The PAB concluded that both CHEC and Kolon- Hansol KECC had not fulfilled the conditions in the bid document. However, three out of the five rejected parties had met the mandatory requiremen­t of proving design experience on sanitary landfill but were rejected “on not fulfilling lesser critical areas such as not giving full details of personnel, equipment, subcontrac­tors and manufactur­ers, etc.”

The PAB recommende­d opening the other five financial proposals; obtaining required clarificat­ions from all bidders; and allowing the SCAPC to negotiate with the bidders who met the essential specificat­ions “with the objective of obtaining a realistic offer, to ensure a tenderer is found within the acceptable cost range”.

As directed by the PAB, the unsuccessf­ul bids were opened in the presence of SCAPC members, a spokesman for the Ministry told the Sunday Times. The parties were not invited because “there was no direction given by the PAB to invite the failed bidders to be present at the opening”.

The offers were appropriat­ely evaluated, the spokesman said. But no negotiatio­ns were conducted with the failed bidders as their “overall responsive­ness was below the acceptable level”. CHECH qualified for because it submitted a letter of intent to form a consortium with the Designer, Southwest Municipal Engineerin­g Design and Research Institute of China (SMEDRIC). Records submitted by the bidder showed that SMEDRIC fulfilled the experience requiremen­t specified in the bidding document.

CHEC together with its design partner, SMEDRIC, scored 947 according to the evaluation criteria specified and predefined in the bid document. The bidding documents did not require the submission of a bid security in the names of all partners if it is in the form of a consortium, the spokesman also claimed.

“The PAB has the right to submit its opinion based on its own analysis,” he said. “However, in the case of this procuremen­t, the responsive­ness of the bid submitted by CHEC was clearly establishe­d giving sufficient clarificat­ions.”

Newspapers in English

Newspapers from Sri Lanka