Sunday Times (Sri Lanka)

PUCSL rejects CEB bid to hire 200MW barge-mounted plant

- By Namini Wijedasa

Electricit­y regulator, Publ i c U t i l i t i e s Commission of Sri Lanka (PUCSL), has denied approval to the Ceylon Electricit­y Board ( CEB) to hire a 200MW barge- mounted plant for anchoring in Galle on an emergency basis.

The PUCSL says the CEB hasn’t submitted informatio­n to justify why it should be exempted from calling for competitiv­e bids for the barge. The ship was to be rented from Karpower Internatio­nal DMCC of Dubai and stationed in Galle for 9 months.

The proposal did not come from the CEB and is not part of the utility’s generation plan. It was initiated by the Power & Energy Ministry, which also sought to station a 300MW barge at Kerawalapi­tiya—that, too, without tender.

There were other issues. The transmissi­on line from Kerawalapi­tiya ( from which power from the 300MW Yugadhanav­i plant run by West Coast Power Ltd, is conveyed to the national grid) does not have sufficient capacity to carry the additional 200MW from the barge.

In Galle, the transmissi­on line is 6 km from the harbour, where the ship will be anchored. This means that another line will have to be drawn from the harbour, completing land acquisitio­n and other procedures in 4 months.

The Attorney General ( AG) previously shot down the power purchase agreement for the Galle barge. He maintained that the Law provides for purchase of electricit­y outside of tender procedure only “to meet any emergency situation, as determined by the Cabinet of Ministers, during a national calamity or a long term forced outage of a major generation plant, where protracted bid inviting process outweigh the potential benefit or procuring emergency capacity required to be provided by any person at least cost”.

“Accordingl­y, it is re-iterated that the determinat­ion of an ‘ emergency situation’ by the Cabinet of Ministers should be done only where there is: a) a national calamity; or b) a long- term forced outage of a major generating plant,” a second AG’s opinion stated earlier this year.

In the past, the CEB has also pointed out that the barge was not specifical­ly approved as an emergency procuremen­t under t h e E l ec t r i c i t y (Amendment) Act.

In a letter to the CEB last week, the PUCSL determines the utility has not sufficient­ly proven that the electricit­y procured from Karpower will be on least-cost terms. Neither has it submitted informatio­n to establish the feasibilit­y of implementi­ng the proposed plant.

The CEB “has not submitted valid informatio­n that could justify the requiremen­t of 200MW capacity addition on an emergency basis for the year 2019,” it reiterates.

Legal requiremen­ts that bind the PUCSL and “the constraint­s imposed by the non-receipt of requested informatio­n to justify the proposed procuremen­t”, made it impossible for the PUCSL to approve the procuremen­t of power from the 200MW barge- mounted power plant at Galle, on an emergency basis, the letter states.

The regulator has also demanded reasons from the CEB as to why it has so far failed to add 320MW of oil-fired power plants, 2 units of 35MW gas turbine power plants, as well as the 122MW Uma Oya power plant to the system in 2018 and 2019. Having added these plants would have further averted the requiremen­t for emergency power.

It is the CEB’s responsibi­lity to ensure there is sufficient capacity available to meet forecasted demand, the PUCSL states. Therefore, it should have initiated tenders on time for the procuremen­t of power plants under the Least Cost Long Term Generat i o n Expansion Plan.

Newspapers in English

Newspapers from Sri Lanka