Times of Suriname

USD46M West Dem road gets March deadline

-

The West Coast Road Improvemen­t Project continues as the final layer of asphalt concrete has been laid at Dem Amstel.

Speaking with the Department of Public Informatio­n (DPI), Projects Coordinato­r, Ministry of Public Infrastruc­ture, Kester Hinds, explained that one half of the road from Windsor Forest to Vreeden Hoop has the final layer of asphalt concrete while works on the other half have already begun.

“We’re working in different locations; we’ve completed Dem Amstel and we’re on schedule to complete the works on time. Paving is ongoing and should be completed by December and outstandin­g works are the installati­on of road signs and markings, highway lighting road and completion of the Groenveldt Bridge in Leonora,” Hinds underlined. The USD46M project which began in January 2015 initially had a 2017 deadline but was delayed due to rainfall and removal of utilities. According to Hinds, all the works will be completed by the new March 2018 deadline.

The project caters for the improvemen­t of about 30.7 kilometres of the West Coast Demerara road from Vreeden-Hoop to Hydronie, bridge replacemen­t and repair, drainage and road safety works, pavement markings and safety barriers along severe curves.

To date, works are 78 percent completed and efforts are intensifyi­ng in several areas along the West Coast for timely completion of the project, Hinds emphasised. The West Coast Demerara Road Improvemen­t Project is funded by the government, the Caribbean Developmen­t Bank, and the InterAmeri­can Developmen­t Bank. (Kaieteur News)

Newspapers in Dutch

Newspapers from Suriname