$uditors probe payment for unfinished health centre

-

The constructi­on of a concrete health centre and living quarters at Wiruni, Berbice River has attracted the attention of state auditors following reports of major financial discrepanc­ies.

Kaieteur News understand­s that Region Ten Regional Democratic Council (RDC) contracted JPM General Contractin­g Services to build the centre at a cost of $14.3M. Reports are that the region paid the contractor $5.9M in 2016 then $3.27M in July 2017. The latter payment attracted the attention of auditors since the constructi­on bond, which is usually utilized when contractor­s default, expired on June 11, 2017. Regional engineer, Clive Peters, was recently questioned on the project by the Public Accounts Committee (PAC) of Parliament. The Committee had concerns about the region’s decision to offer a contract extension for three months in December 2016.

Peters related to the PAC that he did not approve the extension. He said that 70 percent of the work on the building was completed. The Acting Regional Executive Officer at the time, Maylene Stephen, claimed to have written the contractor to offer the three-month extension without a written approval from the Region’s Public Works Department. When regional officials learned that the bond had expired they moved to terminate the contract. While there are concerns about the project, residents continue to await the opening of the much-needed health centre. The building should have been completed since December 2016.

(Kaieteurne­ws)

Newspapers in Dutch

Newspapers from Suriname