Bangkok Post

A $100-billion train: the future of California or a boondoggle?

In the face of sharp opposition and questions about how to pay for it, constructi­on of a high-speed railway is roaring ahead. By Adam Nagourney

-

It is vigorously opposed by Republican­s, including President Donald Trump. It has been plagued by escalating costs and delays. California­ns are mostly against it. And a central question — how is it going to be paid for — remains unresolved.

But here in the Central Valley, far from the debates in Washington and Sacramento, the $100-billion Los Angeles-to-San Francisco bullet train has moved off the drawing board and onto 21 constructi­on sites spread across five Central California counties.

Work began last month on one of the more ambitious pieces of the project — an overpass that will carry trains over a major highway in Fresno — and ground will be broken on three more viaducts in the next few months.

Nearly 2,000 workers are on the job, starting as early as 5am to avoid the 110degree afternoon heat.

“Simply put, dirt is flying in the Central Valley,” the High-Speed Rail Authority declared in a recent business plan.

Yet for all the cranes, crews in orange vests, beeping trucks and fresh concrete, it remains far from certain that this project will ever be completed. In addition to the lack of funding, it faces opposition from both Mr Trump and Representa­tive Kevin McCarthy, the Bakersfiel­d Republican who is the House majority leader.

The continued delays and rising costs have fuelled criticism that California, perhaps the most prosperous state in the United States, is squanderin­g money on a transport project that critics describe as a prime example of big government waste in a state controlled by Democrats.

“This is going to be the most expensive and slowest form of fast rail imaginable,” said Jim Patterson, a former Fresno mayor who is now a Republican member of the state Assembly and a critic of the project.

For all the constructi­on, the project faces the ever-present threat that a future governor may decide that state resources would be better used dealing with, to name one example, the housing crisis. Governor Jerry Brown, a big proponent, is leaving office at the end of the year.

“The project seems to make even less sense today,” said Joe Nathan, a professor of public policy at Stanford University.

For advocates of high-speed rail, California under Mr Brown has been a rare bright spot, while other ambitious government­funded bullet train proposals across the nation have struggled in the face of opposition from Republican­s who are concerned about the costs and disruption­s.

Governor Rick Scott of Florida rejected federal funds to help build a high-speed rail line from Tampa to Orlando, saying it was too expensive for taxpayers. Attempts to upgrade rail service between New York and Boston on Amtrak’s Northeast Corridor have repeatedly faltered because of community opposition.

A high-speed rail line is moving ahead in Texas, connecting Dallas, Fort Worth and Houston, but it is being financed by private industry.

The high-speed train in California, championed by Mr Brown, a Democrat, and Arnold Schwarzene­gger, his Republican predecesso­r, is the most ambitious public transport project under way in the US today. It is moving ahead while other mass transit improvemen­t ambitions — for the subway system in New York City, for an innovative elevated train line in Honolulu — have been hamstrung by costs and opposition.

Mr Brown’s enthusiast­ic backing has been crucial to the project’s advances. Gavin Newsom, the Democratic lieutenant governor and the leading contender to succeed Mr Brown, has offered conflictin­g views of the project over the years; he has at times come close to opposing it outright, though in this campaign he has said he supported it, while expressing concern about costs and engineerin­g challenges.

By contrast, his Republican opponent, John Cox, has pledged unequivoca­lly to abandon the project if elected.

The 800-mile line from Los Angeles to San Francisco is scheduled for completion by 2033. There is no shortage of obstacles to what even the project’s biggest boosters call an ambitious timetable, including the engineerin­g challenge of tunnelling through the Tehachapi Mountains, a barrier between the Central Valley and Los Angeles.

The cost was originally supposed to be split among the state, the federal government and private business. But that arrangemen­t faltered, as hopes for federal dollars faded with Republican­s in power in Washington and businesses shied away from such an uncertain venture.

As of now, the rail authority has come up with less than $30 billion of the necessary $100 billion, and the project’s costs are expected to continue to rise.

“The rest has to be found,” said Martin Wachs, an emeritus engineerin­g professor at the University of California, Berkeley, and a member of a committee appointed by the Legislatur­e to review the project. “At the moment, 100% of the cost is going to be absorbed by the taxpayers.”

Beginning constructi­on without all the financing i n place represents a strategic gamble by the rail authority, and by Mr Brown, that once enough work is completed, future leaders will be loath to walk away from the project and leave a landscape of unfinished pillars, viaducts, bridges and track beds. Faced with reduced resources, the authority has altered its plans and is focused on finishing a 119-mile stretch of track from Bakersfiel­d to Madera by 2022.

Brian P Kelly, the head of the authority, argues that when this stretch of train is completed, people will rally around the project and the business community will become convinced of its viability.

“If I can get trains on the ground, California­ns will start to see that this is something that we want,” he said. “There’s a lot of attention paid to what we don’t have. But we have significan­t fund-raising to get done what we have to get done.

“Yes, the project has challenges,” Mr Kelly said. “And the primary challenge for this same project is the same today as it was the day the voters passed the bond: and that is, we don’t have enough money to build what we want to build.”

In downtown Fresno, more than 300 homes and businesses have been relocated, some by condemnati­on, to make way for the rail line. A mile-long network of viaducts, bridges and platforms is rising more than 60 feet over farmland.

“We had to shift this freeway here over by 100 f eet,” said Diana Gomez, the Central Valley regional director of the California HighSpeed Rail Authority, as she drove down a brand-new stretch of Highway 99 that was rebuilt to make way for the train line just north of this city.

The strategy of concentrat­ing first on the section from Bakersfiel­d to Madera puts off tunnelling through mountains, which Mr Kelly said could cost anywhere from $4 billion to $13 billion. It also means that people living in California’s two major population centres — San Francisco and Los Angeles — will see no sign of the project any time soon.

“The latest business plan is essentiall­y a going-out-of-business plan,” Mr Patterson said. “It finally admits that it cannot complete a high-speed rail plan between San Francisco and Los Angeles. It’s a rump railroad.”

But John Hernandez, an employee with the Small Business Administra­tion who lives in Fresno, said a high-speed train would transform his town, bringing in more visitors and making it easier for him to get to big cities.

“It would change my life,” he said. “I would be able to go places faster. I could get on a train at noon and be in San Francisco at 3pm.”

It has been 10 years since California­ns voted to approve the $9.95-billion bond, a down payment on a project that was estimated at that time to cost $40 billion.

Public enthusiasm is dwindling. While 48% of respondent­s said they supported the project in a USC/Dornslife/Los Angeles Times poll in May, just 31% said they wanted the state to keep building the rail line after they were told of the cost overruns.

Roger Dickinson, executive director of Transporta­tion California, a transit advocacy group, said the obstacles are significan­t but the need for the train is critical: “Looking at the need for increased environmen­tally sound ways of moving people between Northern and Southern California, it’s a project that still makes great sense, and I think it will be successful.”

Karen Philbrick, executive director of the Mineta Transporta­tion Institute at San Jose State University, said the problems were not unlike those that confront any ambitious project.

“Approximat­ely two dozen other countries have found HSR feasible, including Uzbekistan,” she said, referring to highspeed rail. “And there is no reason it can’t be done here.”

It remains entirely conceivabl­e that the state could walk away from the project and put the acquired rights of way and new viaducts to other uses, like convention­al freight or passenger trains. The question is whether the constructi­on on display in the Central Valley will be enough to dissuade a future governor from doing that.

“The more they can show what they have done, the harder it is to abandon the project,” Mr Wachs said. “On the other hand, it can easily be argued that the cost of what they have done so far has so exceeded their projection­s that it’s not inappropri­ate for a governor to look at it and say, ‘Let’s not throw more good money after bad’.”

Mr Kelly said the merits of the project would ultimately pull it through.

“The project has been a political football for some time,” he said. “What I know is this: this project has all the right points of what California is trying to do with transporta­tion. We are trying to provide fast, efficient service, and we are trying to do it in a clean way that expands our economy.”

This is going to be the most expensive and slowest form of fast rail imaginable. JIM PATTERSON Former Fresno mayor

 ??  ?? A viaduct is intended to carry the line over a freeway.
A viaduct is intended to carry the line over a freeway.
 ??  ??
 ?? PHOTOS BY THE NEW YORK TIMES ?? A column supporting a high-speed rail viaduct.
PHOTOS BY THE NEW YORK TIMES A column supporting a high-speed rail viaduct.
 ??  ?? ABOVEWorke­rs install reinforcin­g steel for a bridge across the San Joaquin River. LEFTConstr­uction of a high-speed rail viaduct is well under way at the San Joaquin River in Fresno, California. BELOWWorke­rs fabricate precast beams for the high-speed rail line’s bridges and viaducts at a plant in Hanford.
ABOVEWorke­rs install reinforcin­g steel for a bridge across the San Joaquin River. LEFTConstr­uction of a high-speed rail viaduct is well under way at the San Joaquin River in Fresno, California. BELOWWorke­rs fabricate precast beams for the high-speed rail line’s bridges and viaducts at a plant in Hanford.