Bangkok Post

EA reaffirms plan for 1,000 EV stations

- YUTHANA PRAIWAN

SET-listed Energy Absolute (EA) remains committed to completing installati­on of 1,000 charging stations for electric vehicles (EVs) by 2020 despite postponing the time frame repeatedly.

The target was projected to be completed by 2018 previously, but was extended to 2019.

The charging outlets are operated by Energy Mahanakhon, an EA subsidiary. The company started to install and expand EV charging outlets in 2017 and won investment incentives from the government.

Energy Mahanakhon budgeted 800 million baht for the installati­on plan.

Somphote Ahunai, EA’s chief executive, said the company has installed 500 stations, mainly in Bangkok and major cities.

“EA is optimistic about finishing the 1,000 stations by 2020 because the government accelerate­d the EV scheme to encourage investment in EV charging outlets,” he said.

“The Energy Ministry is considerin­g power tariffs for EV charging stations to support this new business.”

Energy Minister Sontirat Sontijiraw­ong said wheeling charges and other regulation­s involved with power distributi­on have been revised to facilitate the EV charging business.

Power distributi­on is operated by two state agencies: the Metropolit­an Electricit­y Authority (MEA) and the Provincial Electricit­y Authority. Private companies are not allowed to sell electricit­y directly to customers, rendering the EV charging business nonexisten­t.

EA is poised to shift gears to become a charging service provider and EV and component manufactur­er. The company has diversifie­d from biofuel production and renewable power generation.

EA operates wind and solar farms with a combined capacity of 664 megawatts as of mid-2019.

The company acquired a 77.21% stake in Taiwan-based Amita Technologi­es during 2017-18 in a deal worth 3 billion baht to start production of EVrelated technologi­es: energy storage systems (ESS) and lithium-ion batteries.

EA expects to begin developmen­t of a lithium-ion battery production plant, including ESS, in 2020, with a planned budget of 5 billion baht in Chachoengs­ao.

The first phase will have a capacity of 1GWh and commence commercial operations in the second half of 2020 after receiving investment privileges from the Board of Investment.

The output from this phase will serve as components to be installed in EVs and for power generation.

The second phase is estimated to cost 98 billion baht and comes with a total capacity of 49GWh.

EA, MEA and Chulalongk­orn University have teamed up to establish a peer-to-peer power trade in the university’s smart city from solar rooftops on 20 buildings. This three-year plan has already started developmen­t.

The university will install ESS to stabilise power generation. Chulalongk­orn aims to have the largest capacity in peer-to-peer power trade in the near future.