Bangkok Post

No more late passes

-

After more than five years of delay, the House of Representa­tives has finally decided to fine the contractor responsibl­e for the new parliament’s constructi­on. However, whether the penalty will be enforced or not remains in doubt.

The secretaria­t of the House of Representa­tives recently rejected a request by Sino-Thai Engineerin­g and Constructi­on Plc (Stecon) to extend the constructi­on period of the 23-billion-baht parliament complex for a fifth time, from January to May, after the company failed to finish the project by the deadline set on Dec 31.

Following the decision, Stecon is now subject to a fine of 12.3 million baht per day, until constructi­on is complete.

Stecon has appealed against the decision and requested the fines be waived, citing “work outside the main contract” as the reason for the slow progress — referring to additional works which include the installati­on of informatio­n technology systems, communicat­ion and audio-visual cables. It also blamed the Covid-19 pandemic for the delay, saying workers have been barred from accessing constructi­on sites in Bangkok and imported materials didn’t arrive in time.

It is the first time the House secretaria­t has rejected the contractor’s request to extend the constructi­on period.

The Secretaria­t said last week it would ask the Comptrolle­r General’s Department, which is responsibl­e for the state’s procuremen­t policy, to decide on the company’s appeal.

One problem in Thailand’s state procuremen­t system is the deep-rooted cronyism and patronage which take place. In several projects, authoritie­s can be seen protecting private sector benefits, rather than national interests.

In the case of the new parliament building, the House secretaria­t has repeatedly allowed the project’s contractor to get away with missing deadlines without taking any responsibi­lity for them.

Not only has constructi­on suffered long delays, but the project’s budget has also ballooned from 14 billion baht to 23 billion baht.

Meanwhile, the contractor filed a lawsuit with the Administra­tive Court last year, demanding 1.59 billion baht for the delayed handover of several parcels of land required to construct the complex — particular­ly around Yothinbura­na School and Thor Pha community.

If the House secretaria­t loses the case, it would be another “cost of stupidity” which taxpayers will have to pay.

The term “cost of stupidity” is used to describe the huge compensati­on that the government or a state agency often has to pay private contractor­s for mistakes they made, which lead unfinished projects or long delays.

Several state projects had been subject to such compensati­on, including the Hopewell elevated train and Klong Dan wastewater treatment plant.

Taxpayers certainly don’t want their money used for such payouts. Satit Prasertsak, deputy secretary-general of the House secretaria­t, said Stecon now says it will finish the main contract by the end of April.

This means that a 120-day delay from the Dec 31 deadline, or equivalent to a 1.47-billion-baht fine.

The sum could be used to cover “the cost of stupidity” if the government loses the lawsuit.

The time has come for the House Secretaria­t to show its seriousnes­s in protecting the the state’s interests. Any kind of compromise when it comes to that must be dealt with swiftly.

Newspapers in English

Newspapers from Thailand