Key numbers with a sustainable hum
Phase 3 Capacity of 800MW
Inaugurated on April 30
1st Stage of Phase 3 200MW
Can power 60,000 homes
Can bring savings of 270,000 tonnes of carbon emissions every year
Completed with over 2.4 million accident-free man hours
2nd Stage 300MW, due in 2019 3rd Stage 300MW, due in 2020
Other Phases
Phase 1 13MW Operational since October 22, 2013
Saves 15,000 tonnes of carbon emissions
Phase 2 200MW Operational since March 20, 2017
Can power 50,000 homes
Reduces 214,000 tonnes of carbon emissions
Phase 4: Concentrated Solar Power (CSP) Project with 700MW capacity
Broke ground on March 19, 2018
Expected to generate power by the end of 2020 and provide clean energy to 270,000 homes
Will help reduce 1.4 million tonnes of carbon emissions annually
Total planned production capacity of MBR Solar Park: 5,000MW by 2030
It is expected to generate 1,000MW by 2020
Total investments: Dh50 billion Total carbon emission savings:
6.5 million tonnes annually
Total size 85 sq km Dubai’s total installed capacity: 10,200MW
Share of solar power as of May 2018: 413MW or 4 per cent