Fukushima reactor ‘ice wall’ nearly finished

-

tokyo — Fukushima’s operator on Tuesday started freezing the last section of a $320 million ice wall designed to combat widespread water contaminat­ion at the site of the worst nuclear accident in a generation.

Tokyo Electric Power (TEPCO) began pumping coolant into the remaining seven metres of its 1.5-kilometre undergroun­d wall which encircles the four reactors along Japan’s northeast coast.

Undergroun­d pipes circulate the coolant and freeze soil around the buildings.

The 30-metre deep wall is designed to block undergroun­d water from nearby mountains from flowing into the shattered complex and then seeping into the Pacific.

It is reportedly expected to take more than two months until the wall is completely frozen.

The huge utility has been building the barrier since March 2016 with the government picking up its 34.5 billion yen ($320 million) price tag.

Even now, with the ice wall almost complete, about 140 tonnes of undergroun­d water flows into the plant daily, forcing the company to pump it out and store it in on-site tanks.

“When the ice wall is completed, we estimate that the amount of undergroun­d water flowing into the complex will be less than 100 tonnes,” a company spokesman said. —

When the ice wall is completed, we estimate that the amount of undergroun­d water flowing into the complex will be less than 100 tonnes A company spokesman

 ?? AFP ?? Workers open valves as they pour coolant to freeze the ice wall around the Fukushima Daiichi nuclear power plants in Okuma. —
AFP Workers open valves as they pour coolant to freeze the ice wall around the Fukushima Daiichi nuclear power plants in Okuma. —

Newspapers in English

Newspapers from United Arab Emirates