March 6, 2007

The UAE and France sign a deal to build Louvre Abu Dhabi

October 10, 2007

The French National Assembly approves the project

May 26, 2009

Piling works completed

Constructi­on works officially starts

August 3, 2010 October 29, 2011

TDIC announces delay in project completion

January 25, 2012

New deadline set as 2015

January 8, 2013:

TDIC awards museum’s main constructi­on contract to Arabtec-led joint venture with Constructo­ra San Jose and Oger Abu Dhabi

December 5, 2013

The first element of the museum’s canopy lifted into place

March 17, 2014

First permanent gallery structure completed

October 22, 2014

Museum’s dome structure installati­on gets completed

June 15, 2016

Temporary sea protection walls removed

December 3, 2016

French President Francois Hollande reviews work progress

September 6, 2017

Museum opening date announced

 ??  ?? Inside the museum, the multi-layered geometric dome of eight superimpos­ed layers creates a dramatic play of light and shadow.
Inside the museum, the multi-layered geometric dome of eight superimpos­ed layers creates a dramatic play of light and shadow.

Newspapers in English

Newspapers from United Arab Emirates