The National - News

UAE’s push on solar should inspire the wider world

- ROBIN MILLS Robin Mills is CEO of Qamar Energy, and author of The Myth of the Oil Crisis

The UAE is getting used to setting solar energy records.

Dubai’s latest project, awarded last Saturday, follows this pattern. But, as a leap forward in a different type of solar power plant, it has important implicatio­ns for renewable energy across the region.

A joint venture of Saudi Arabia’s Acwa – already very involved in solar and coal projects with Dubai Electricit­y and Water Authority and across the region – and China’s Shanghai Electric, will build the fourth phase of the Mohammed bin Rashid Al Maktoum Solar Park, as the world’s largest concentrat­ed solar power (CSP). It is sometimes called a solar thermal plant.

What has made headlines is the world-record low price for this type of technology: 7.3 US cents per kilowatt hour (kWh) of electricit­y generated. This equates to a total cost of Dh14.2 billion for 700 megawatts (MW) of capacity, about 7 per cent of the utility’s current capacity.

CSP is different from the three photovolta­ic (PV) plants awarded so far in the solar park. Photovolta­ic panels use light falling on a semiconduc­tor to dislodge electrons and create a current. CSP plants concentrat­e the sun’s rays with mirrors to heat a fluid, which then drives a turbine in a similar way to a convention­al gasfired power station.

Masdar constructe­d what was then the world’s largest CSP plant, the 100MW Shams 1 near Madinat Zayed in 2013.

Other plants have been built in Spain, Italy and United States, but the technology lost favour as PV costs plunged.

At the time Shams 1 started, PV projects in the UAE may have cost around 12 US cents kWh. More recently the 800MW third phase of Dewa’s solar park was bid at 2.99 US cents, and the 1,177MW Sweihan plant near Abu Dhabi for 2.4 cents. Even this latest CSP project for Dewa costs about three times that. However, interest in CSP has remained because of its ability to store energy in molten salts, and continue generating even at night.

PV cannot do that except with batteries, which remain relatively expensive. Dewa’s plant is divided into two parts: a central tower, with storage for 15 hours of operations; and parabolic troughs with 11 hours of storage.

Worldwide, towers are becoming more popular choices for CSP because their higher operating temperatur­es make them more efficient and facilitate longer storage periods.

Hydrocarbo­n-short Morocco has been the Mena region’s leader in CSP so far. Up in its Atlas mountains, it has constructe­d one CSP plant at Ouarzazate, with two more underway. The location is at an altitude of more than 1,150 metres, with clear skies and a river nearby to supply water.

Dubai’s site is close to sea-level, with more atmosphere to absorb the sun’s rays, as well as the Arabian Gulf’s dust and haze. The Noor 2 CSP plant at Ouarzazate – also being built by Acwa – has only 7 hours storage, half of Dubai’s. Yet the low bid for Noor 2 was 15.67 cents kWh, while Dubai has managed to halve that.

Evaluating the project properly will require more informatio­n: How much of the 15 hours’ storage is at maximum output, and what the plant’s capacity factor will be (the ratio of actual output to the output if it could run continuous­ly through a year)?

It will be interestin­g to learn how Acwa has managed to cut costs so dramatical­ly, and to see how well the plant performs.

The project is a major step forward, not just for Dubai but for the region.

Dubai’s target of 7 per cent clean electricit­y by 2020 should be met when this plant starts up late that year, along with the earlier PV projects. Dewa is already looking ahead to the challenge of balancing large amounts of daytime solar generation while meeting night-time demand. If this CSP plant functions well at the anticipate­d cost, it will go a long way to solving that problem.

Any Middle East country with sufficient flat, unused land – everywhere with the possible exceptions of Bahrain and Lebanon – could install large amounts of solar thermal power. Western Saudi Arabia, Jordan and Egypt have, in principle, better conditions than Dubai, but it is Dubai that has so far created the best investment propositio­n.

CSP at 7.3 cents kWh is equivalent to a gas-fired power station buying gas at US$5 to $6 per million British thermal units (MMBtu). Spot liquefied natural gas (LNG) prices in August were around $5.8 per MMBtu, and are expected to rise somewhat over the next few years. This is more expensive than traditiona­l Middle East subsidised prices. But it does indicate that a combinatio­n of solar PV and CSP is a realistic alternativ­e to gas for electricit­y in this region.

All regional utilities ought to be watching closely. If they can convince themselves that Dewa’s price is realistic and replicable for their conditions, CSP should be part of their future generation plans. Countries that are moving ahead with solar power, such as Morocco, Tunisia, Egypt and Jordan, can press on.

Others who have made little progress, notably Saudi Arabia, should be encouraged to jump-start their efforts.

If new solar PV records were becoming passé, this latest project should open eyes across the Middle East.

It will be interestin­g to learn how Acwa has managed to cut costs so dramatical­ly, and to see how well the plant performs

 ?? LeAnne Graves / The National ?? Concentrat­ed solar power towers at the Noor plant in Morocco
LeAnne Graves / The National Concentrat­ed solar power towers at the Noor plant in Morocco
 ??  ??

Newspapers in English

Newspapers from United Arab Emirates