The National - News

Oman targets phase two of its solar thermal plant in two years

- JENNIFER GNANA

One of the world’s largest solar thermal plants to recover heavy oil reserves in Oman is targeting for phase two expansion in 2019, with future plans to manufactur­e aluminium mirrors domestical­ly, according to the operator Petroleum Developmen­t Oman (PDO).

“We’ll complete the first module (four glasshouse­s) this year and by the beginning of 2019 another two modules – comprising eight glasshouse­s – [will be completed] and we’ll go for phase two in 2019,” said PDO external affairs and value creation director Abdul-Amir Al Ajmi.

“In phase three, we plan to manufactur­e and produce aluminium used in the mirrors and glasshouse in Oman. The very fine aluminium that is used in building mirrors is currently brought from China,” he added.

One of the Arabian Gulf’s smaller producers, non-Opec member Oman sits atop heavy oil reservoirs in maturing fields, which require steam, gas or polymer injection to recover crude.

With gas being in short supply in the sultanate, PDO has embarked on a programme to recover heavy reserves from its southern Amal oilfield using solar power generated steam through its joint venture with the US company Glasspoint.

The 1,021-megawatt (MW) facility called Miraah – Arabic for mirror – is set to generate 6,000 tonnes of steam daily and is the Middle East’s first enhanced oil recovery programme to tap into solar energy.

“Phase one is supposed to finish by end of the year and we’re already integratin­g it with the steam network,” said Mr Al Ajmi.

The US$600 million project will comprise 36 blocks (nine modules) concentrat­e the sun’s rays and generate steam, saving around 5.6 trillion British Thermal Units of natural gas annually, which will be deployed towards power generation.

“Gas is becoming very expensive and we suffered shortages of gas in the past. By using solar, which is free, we generate steam, which will then be injected into the reservoir to get oil recovery,” said Mr Al Ajmi.

The upstream operator’s ongoing major projects, the $1.25 billion Rabab Harweel Integrated Project to produce six million cubic metres a day of sweet gas and 60,000 barrels per day (bpd) of oil, as well as the $900m Yibal Khuff project to deliver five million cm/d of associated gas and 10,000 bpd of oil, are on track for completion in 2019 and 2020, respective­ly, he added.

“We’re not deferring projects per se but we’re spending more time to study them, how to bring their costs down to meet the current environmen­t.

If you talk about major projects, we’re building the largest oil project in PDO’s history at Rabab Harweel area because it contains sour gas, also Yibal Khuff. Both projects are on time and on schedule,” said Mr Al Ajmi.

 ?? Getty ?? PDO has embarked on thermal plant project because gas is in short supply in Oman
Getty PDO has embarked on thermal plant project because gas is in short supply in Oman