Egypt opens first plant at $2.8bn Benban Solar Park in Aswan

-

Egypt inaugurate­d the first solar power plant at a remote desert complex where the government plans to generate as much as 1.8 gigawatts from the Sun, cutting the most populous Arab nation’s reliance on dirty and expensive fossil fuels.

The plant, developed by German Ib Vogt and a local company called Infinity Solar Systems, began supplying the national grid in December, Ib Vogt chief executive Anton Milner said on Tuesday. The 64MW facility is the first of 32 units that the government targets for constructi­on at Benban Solar Park in southeaste­rn Aswan province. The project, with all the plants, is to be completed next year at a cost of $2.8 billion.

“In this plant, we have 200,000 solar panels and 780 sun trackers that allow the panels to move toward the solar position throughout the day,” Amine El Edghiri, Ib Vogt’s project manager, said during a media tour of the facility 650 kilometres south of Cairo on the fringes of the Nubian Desert. The photovolta­ic modules arrayed across 235 acres can produce enough power to supply 20,000 households, Mr El Edghiri said.

Egypt currently produces more than 90 per cent of its power from oil and natural gas, according to data from Bloomberg New Energy Finance. Benban Solar park, along with other projects in planning, should help Egypt scale back its use of hydrocarbo­ns as the country targets generating 20 per cent of its electricit­y from renewables by 2022.

Formerly a gas exporter, Egypt must now import liquefied natural gas, or LNG, at a high cost to meet its energy needs. New gasfields that have started production, including the giant offshore Zohr field operated by Eni, should help the country close its supply gap, trim its import bills and maybe even resume exports. Solar and wind energy projects will help transform the country’s power mix.

Egypt’s first round of socalled feed-in tariffs for solar power led to the installati­on of fewer than 200MW of projects, out of several gigawatts of applicatio­ns, due to commercial terms that many investors considered onerous. The government amended its terms in the second phase of the tariff programme, including a change to allow internatio­nal arbitratio­n, to try to entice a greater number of foreign lenders and investors.

The second phase was more successful, with many projects securing financing. Improvemen­ts in technology making it cost-effective for investors to exploit the country’s abundant sunshine also made a difference.

Most countries are avoiding feed-in tariffs for competitiv­e tenders that force developers to bid against each other for projects. Egypt issued its first competitiv­e solar auction late last year to build a 600MW plant in the West Nile region as it tries to drive down the cost of clean energy. The auction has attracted 18 applicants.

“It’s a natural progressio­n,” Mr Milner said. “The auction-based schemes will basically be more competitiv­e.” His company plans to build three more units at Benban and connect them all with the national grid as early as the fourth quarter, he said.

Other developers building plants at the solar park include Scatec Solar of Norway, Francebase­d EDF Energies Nouvelles and Total Eren, and Access Power MEA from Dubai and Saudi Arabia-based Acwa Power and Al Fanar.

In this plant, we have 200,000 solar panels and 780 sun trackers that allow the panels to move toward the solar position AMINE EL EDGHIRI Ib Vogt project manager

 ?? Corbis ?? The 64MW facility is the first of 32 units that the government targets for constructi­on at Benban Solar Park
Corbis The 64MW facility is the first of 32 units that the government targets for constructi­on at Benban Solar Park