Gareth grates as the A83 surface plans reschedule­d

-

The arrival of Storm Gareth earlier this week forced BEAR Scotland to rethink plans to resurface six stretches of the A83 trunk road.

The £375,000 project was due to start at the Rest and be Thankful on Sunday March 10 but as snow fell this was postponed pending a review on Monday March 11.

Trunk road management firm BEAR Scotland later announced the schedule had been revised following ‘forecast inclement weather’.

The decision taken was to postpone resurfacin­g at the Rest until Sunday March 17.

Overnight resurfacin­g at the A83 Inveraray Bridges was due to start on Thursday March 14, with drivers facing lengthy diversions via Crianlaric­h.

Three nights of closures are planned at the Rest and be Thankful from Sunday March 17 to Tuesday March 19 from 8pm to 5am each night.

The adjacent old military road diversion route will be in place and motorists should allow extra time for journeys.

Attention will then turn to Strone Point for resurfacin­g overnight on Wednesday March 20 from 7pm to 7am. An overnight road closure will be required, with drivers once again facing a detour via Crianlaric­h.

On the A83 south of Whitehouse, resurfacin­g will take place on Thursday March 21 between 7pm and 7am.

The road will be closed, but traffic will be allowed to pass at 8pm, 9pm, 10pm, midnight, 2am and 4am. Motorists are encouraged to arrive prior to these times to ensure they can get through.

Four nights of work will take place at Stonefield from Sunday March 24 to Wednesday March 27, between 7pm and 7am. The road will be closed, but opened to let traffic pass at 8pm, 9pm, 10pm, midnight, 2am and 4am.

Local access and access for emergency services will be maintained at all times. On Friday March 29, work will be carried out on the A83 Shira to Inveraray Bridge between 7am and 7pm. The road will remain open with a convoy system in place.

 ?? 51_a11RestSno­w02 ?? The scene at the Rest on Sunday afternoon as resurfacin­g work was postponed. It will now take place from Sunday March 17.
51_a11RestSno­w02 The scene at the Rest on Sunday afternoon as resurfacin­g work was postponed. It will now take place from Sunday March 17.