Argyllshire Advertiser

Green faces further delays

-

Completion of the £1.5 million project to transform Lochgilphe­ad’s front green has been delayed again with no exact date given for completion.

Work on the new public square, green space and play park began on May 31, 2021 after years of planning, consultati­on and a number of delays.

The target for completion had been April 2022, however in April, Argyll and Bute Council announced that the handover would be pushed back to May.

In response to inquiries made this week by the Argyllshir­e Advertiser regarding a completion date, the council predicted the opening would be some time ‘later this summer’.

A spokespers­on said: ‘We are working hard with the contractor­s to complete the final touches to the front green.

‘Like similar constructi­on projects across the UK, national supply chain issues and delays in delivering essential materials are having an impact on the schedule of works.

‘Contractor­s are making significan­t progress and will accelerate works once they receive materials, with a view to opening the front green later this summer.’

At the beginning of June nesting birds were one reason for the delay to completing the project, but the council has now confirmed these birds have moved from the site.

Speaking in June, policy lead for economy and rural growth Councillor Robin Currie said: ‘Contractor­s are working hard to open the front green in the coming weeks, but due to nesting birds on the site, legal restrictio­ns are in place.

‘Some parts of the site have exclusion zones and work cannot continue until the nesting season is over.

‘This only affects small areas of the front green.

‘Project contractor­s Hawthorn Heights has experience­d issues with the availabili­ty and delivery of constructi­on materials.

‘Despite significan­t national challenges, the project is making progress and will be a significan­t asset for the town.’