Anti-HS2 protests cost the taxpayer £80 million

-

DEALING with anti-HS2 protests has cost the high-speed rail project up to £80 million, the Government has announced.

Environmen­tal activists have caused disruption at several sites on Phase One of the line between London and Birmingham.

An expensive month-long operation was required to remove people from a network of tunnels in London’s Euston Square Gardens earlier this year.

In a statement to Parliament, HS2 minister Andrew Stephenson wrote: “With regard to protester activity, which HS2 Ltd estimates has cost the project up to £80 million, the Government is making sure that HS2 Ltd, its supply chain, emergency services and wider government have a co-ordinated response to illegal protest.

“Regrettabl­y, some protesters have turned to violent and aggressive behaviour, particular­ly against HS2 Ltd’s supply chain.

“The Government is taking steps to ensure that illegal protester activity is properly dealt with and that safety risks are minimised.”

Mr Stephenson said HS2 is facing “cost pressures of around £1.3 billion,” up from the figure of £800 million given in his previous update in March.

Some £600 million is due to the “slower than expected mobilisati­on” of constructi­on contracts partly due to delays with completing preparator­y work, approving designs and securing planning consents.

A further £400 million is due to difficulti­es with redevelopi­ng Euston station.

Mr Stephenson explained that the costs may need to be covered by contingenc­y funds contained within HS2’s existing £44.6 billion budget (at 2019 prices) for Phase One agreed last year.

The Government-commission­ed Oakervee Review warned in 2018 that the final bill for HS2 could reach £106 billion (at 2019 prices). Despite it running tens of billions of pounds over its initial budget and several years behind schedule, Boris Johnson gave HS2 the green light in February 2020.

A Department for Transport spokeswoma­n said: “HS2 Phase One remains within its schedule and budget. Delivering a major project of the scale and ambition of HS2 will always be challengin­g but, as today’s parliament­ary report sets out, current cost pressures, if they materialis­e, will be covered within our existing budget.

“This project is at the heart of our plans to build back better, supporting more than 20,000 jobs.

“We are committed to maintainin­g a tight control of costs and HS2 Ltd continues to identify areas across the project where savings and efficienci­es can be made.”