Extra £1m for roads and pavements

- ANTHONY LEWIS anthony.lewis@reachplc.com

AN EXTRA £1m worth of road and pavement improvemen­ts are planned in the borough this year.

The council will spend £883,000 on an extra 25 carriagewa­y improvemen­t projects and £413,000 on an extra 12 footway schemes, a total extra expenditur­e to almost £1.3m.

This is in addition to its previously approved capital programme for 2019-20 which includes £6.3m for carriagewa­ys and £1.5m for pavements across RCT.

Speaking at the cabinet meeting which approved the extra schemes on Tuesday, June 18, council leader Andrew Morgan said it was part of a £23.5m three-year investment programme in roads and pavements.

He said the council’s capital budget in previous years had been about £1m, but with the additional schemes and those already approved, it is now £8m.

These are the extra carriagewa­y schemes approved by the council:

£25,000 – composite on Heol y Mynydd, Aberdare

£55,000 – overlay on access to Ferndale High School, Ferndale

£60,000 – strengthen­ing Aberdare Road, Blaenllech­au

£65,000 – strengthen­ing Berw Road, Tonypandy

£55,000 – strengthen­ing Victoria Street, Penrhiwcei­ber

£26,000 – strengthen­ing Bradley Street, Abercynon

£28,000 – strengthen­ing Hamilton Street, Mountain Ash

£25,000 – composite on Blaengwawr Close, Aberaman

£40,000 – microaspha­lt on Danygraig Crescent and Danygraig Drive, Talbot Green

£30,000 – strengthen­ing Pleasant Street, Pentre

£45,000 – strengthen­ing Llanharry Road, Brynsadler

£55,000 – microaspha­lt on Penrhiwcei­ber Road, Penrhiwcei­ber

£30,000 – microaspha­lt on Pant-y-cerdin, Cwmbach

£60,000 – strengthen­ing Upper and Lower Terrace, Stanleytow­n

£34,000 – composite on Brookfield Lane, Pontypridd

£20,000 – strengthen­ing Coedpenmae­n Road, Pontypridd

£25,000 – microaspha­lt on John Street, Abercwmboi

£10,000 – microaspha­lt on Bryncoch, Taff’s Well

£15,000 – strengthen­ing Hughes Street, Penygraig

£40,000 – strengthen­ing Rose Row, Cwmbach

£30,000 – strengthen­ing Hillcrest Drive, Porth

£25,000 – strengthen­ing Seaton Street, Pontypridd

£10,000 – overlay on Partridge Road and Church Street, Llwynypia

£35,000 – strengthen­ing Stanley Road and Smith Street, Gelli

£40,000 – strengthen­ing Ynysmeurig Road, Abercynon

And there are 12 extra footway schemes, including a £110,000 tarmac of Coed Isaf Road in Pontypridd.

Other tarmac works include £80,000 for Yorkdale Estate in Beddau, £30,000 for Danygraig Crescent and Drive in Talbot Green, £30,000 for Bryncoch in Taffs Well, £30,000 for Milbourne Street in Penygraig, £28,000 for Tegfan in Ferndale, £15,000 for Coedpenmae­n Road in Pontypridd and £15,000 for Hillcrest Drive in Porth.

There are access improvemen­ts planned, including £20,000 for Meadow Street and Park Street in Trefforest, £20,000 for Station Road in Hirwaun and £15,000 for Gelli Terrace in Gelli.

The final footway project is £20,000 for slabs on Collwyn Street in Coedely.

 ?? GOOGLE ?? RCT Council is planning major road and pavement improvemen­ts
GOOGLE RCT Council is planning major road and pavement improvemen­ts