Cynon Valley

Road project cost concerns

- RHODRI CLARK newsdesk@walesonlin­e.co.uk

THERE are concerns that poor preparatio­n and “over-engineerin­g” could increase the cost and disruption of dualling the last single-carriagewa­y section of the A465, between Dowlais and Hirwaun.

THERE are concerns that poor preparatio­n and “over-engineerin­g” could increase the cost and disruption of Wales’ biggest road scheme.

Some of the geological survey work for dualling the last single-carriagewa­y section of the A465, between Dowlais and Hirwaun, was not carried out until last autumn, more than a year after procuremen­t of contractor­s began. In at least one case, explorator­y drilling has been postponed until constructi­on is under way.

The scheme will follow dualling of the same road between Gilwern and Brynmawr – where unforeseen engineerin­g difficulti­es have increased the cost and prolonged the disruptive roadworks.

However, the Welsh Government says that lessons from that scheme have been applied to the new scheme, and that the recent drilling was to supplement informatio­n from previous boreholes.

The government expects dualling of the Heads of the Valleys road west of Dowlais to be completed in phases from 2022-23 onwards. The constructi­on cost – estimated at over £500m when VAT is included – will be covered by private finance, repaid by the government in annual service payments over 30 years.

The level of annual payments will reflect, among other things, any risk of unforeseen engineerin­g challenges.

Procuremen­t of the contractor is now close to completion. It began in July 2018, but it was not until September 2019 that engineerin­g consultant­s acting for the government contacted householde­r Michael Burke, who lives near the A465, for permission to drill an explorator­y borehole on his land.

Subsequent­ly, the road scheme’s ecological advisers said the drilling should not take place in autumn to avoid disturbing wildlife.

The consultant­s explained: “We will not be drilling the borehole on your land due to ecological constraint­s; this borehole will be picked up during the main constructi­on works phase.”

Mr Burke said he had already formed the impression the scheme was poorly prepared from attending the public inquiry last year and his previous dealings with officials. Now he fears the scheme could repeat some of the problems encountere­d on the Gilwern to Brynmawr section.

“Everybody accepts that it [Gilwern to Brynmawr] is a classic case of incompeten­ce,” he said. “It’s dramatical­ly over budget. If they had done the ground investigat­ions properly, they would have known what they were coming up against.”

He thought that obtaining a detailed understand­ing of the geology along the Dowlais to Hirwaun route would have been important because the area was riddled with caves and undergroun­d watercours­es.

Graham Thomas, county councillor for Rhigos, supports the principle of dualling the road on safety grounds, but objected during public consultati­on to the layout of the proposed new junction between the A465 and various local roads at Croesbycha­n.

The original plans had shown four roundabout­s clustered around the junction, which would have taken up excessive land, Mr Thomas believes.

“That was an overengine­ered solution,” he said. “They came down to the present situation where we [will] have three roundabout­s. We said it should be two roundabout­s. We failed on that one.”

He said the A465 had been closed at night over two months in the autumn for borehole drilling.

He hoped that the engineers understood the conditions by now. “If they don’t, it’s getting rather late in the procedures,” he said.

A government spokesman said extensive boreholes were drilled in the 1990s and 2015, providing informatio­n for bidding organisati­ons before procuremen­t started.

“The recent ground investigat­ion contract scope was developed with detailed input from all three bidders to ensure their individual borehole requiremen­ts and priorities were included.

“Bids for the project will not be compromise­d by a lack of geological data.

“Ground condition risk rests with the bidders under the terms of the contract.

“It is important bidders understand the nature of the ground conditions to enable them to accurately price that risk.”

Asked why at least one borehole was postponed until constructi­on, he said: “Every effort has been made to complete the entire scope of ground investigat­ions.

“All the priority areas identified by bidders have been completed and some further non-priority areas will be completed prior to constructi­on, as the constraint­s allow.”

Regarding changes to the Croesbycha­n junction layout after local criticism, he said the arrangemen­ts were developed in conjunctio­n with the local authority and “adjusted following considerat­ions at the public inquiry”.

He said lessons learned from the Gilwern to Brynmawr section had been incorporat­ed in the Dowlais to Hirwaun procuremen­t, where the contract would include strict restrictio­ns on traffic management during constructi­on.

The procuremen­t had used “competitiv­e dialogue”, where bidders discussed “value engineerin­g” opportunit­ies.

 ??  ?? Widening the A465 Heads of the Valleys road between Brynmawr and Gilwern was originally planned to cost £220m
Widening the A465 Heads of the Valleys road between Brynmawr and Gilwern was originally planned to cost £220m

Newspapers in English

Newspapers from United Kingdom