Cynon Valley

Rail upgrade gets moving

- RHODRI CLARK newsdesk@walesonlin­e.co.uk

THE long-awaited £738m modernisat­ion of the Core Valley Lines – to provide faster, more frequent and less polluting services to Cardiff – has started in earnest after Network Rail transferre­d infrastruc­ture to the Welsh Government.

THE long-awaited modernisat­ion of the Core Valley Lines has started in earnest after Network Rail transferre­d the infrastruc­ture to the Welsh Government.

The £738m investment will result in new tramtrains and tri-mode trains using overhead electric supply and on-board batteries to provide faster, more frequent and less polluting services to Cardiff from Aberdare, Merthyr Tydfil, Treherbert and Rhymney.

The transfer of assets also covers the Cardiff Bay and Coryton lines and the City Line, between Radyr and Ninian Park.

The Welsh Government is now owner of the tracks, signalling, bridges and stations. The formal transfer process was triggered in late January.

The Government will give Transport for Wales and Amey Keolis Infrastruc­ture Ltd (AKIL) the task of modernisin­g and operating the infrastruc­ture as well as running the train services, using the existing trains until the new ones are phased in.

The Government originally expected the transfer to happen in September. The six-month delay has compressed the time available for the engineerin­g work. Tram-trains need to be in service by the end of 2022 to ensure the Government receives the European Union’s promised contributi­on to the modernisat­ion in 2023.

The Rhymney and Coryton lines are scheduled for completion by the end of 2023. Their trimode trains will use overhead and battery electric supplies north of Cardiff Queen Street.

They will need diesel engines to continue providing through services to places such as Penarth and Barry where the infrastruc­ture will remain owned by Network Rail and the UK Government, which has turned its back on further railway electrific­ation.

TfW and AKIL have used the six-month delay to fine-tune designs for the new Core Valley Lines (CVL) infrastruc­ture, reducing the risks of glitches when work is under way.

Karl Gilmore, rail programme director at TfW, said Network Rail had allowed access for preparator­y works alongside the CVL over the past year. These works including clearing vegetation and tackling invasive species, particular­ly Japanese knotweed.

At Treforest, an infrastruc­ture hub has been opened for distributi­on of constructi­on materials across the CVL. Alongside Taff’s Well station, industrial buildings have been cleared and constructi­on has started on a £100m tram-train depot and CVL control centre.

Passengers should start to see the first foundation­s for the electrific­ation masts appearing this summer.

“A section of track in the vicinity of Taff’s Well will be commission­ed first, to allow testing of some rolling stock,” said Mr Gilmore.

“In general, the Treherbert, Aberdare and Merthyr lines will be developed first, followed by the Rhymney line.”

However, TfW is considerin­g whether to bring forward some of the work on the Rhymney line.

Mr Gilmore said some of the CVL engineerin­g work would be carried out on weekday nights. Some would need closures of lines on weekends or for longer periods, with bus replacemen­t services for passengers.

The work should cause less disruption to passengers and communitie­s than the recent electrific­ation of the main line from the Severn Tunnel to Cardiff, where road bridges over the railway had to be rebuilt to provide more clearance for the 25kV electricit­y supply.

The CVL’s overhead equipment will be electrical­ly isolated under each bridge, where the trains will automatica­lly switch to battery power before reverting to overhead power supply after the bridge.

This will avoid disruptive rebuilding of bridges.

It also means there is no need to install electrific­ation equipment in Caerphilly Tunnel, which otherwise could have been closed for weeks or months.

Additional track will be installed at locations north of Bargoed, Abercynon and Porth for the frequency of trains to be increased to four per hour per direction on what is predominan­tly a single track.

Key challenges for TfW and AKIL are testing the new trains and power supply to prove that they are safe and reliable, and integratin­g the modernised CVL with Network Rail’s infrastruc­ture, signalling and operationa­l control.

The same processes are taking much longer than expected on the Crossrail project in London, and TfW’s board was alerted to the similariti­es in December.

The board “agreed the importance of learning lessons” from Crossrail.

An independen­t reviewer has told TfW its plans for the CVL are similar to Crossrail in some respects, but also said TfW has a strong team in place and there is time to solve outstandin­g issues.

 ??  ?? The modernisat­ion of the Valley Lines is set to start in earnest
The modernisat­ion of the Valley Lines is set to start in earnest

Newspapers in English

Newspapers from United Kingdom