Evening Telegraph (First Edition)

Roadworks come to an end after a long delay

- BY JAKE KEITH

ROADWORKS on a Dundee city centre street costing about £650,000 are set to come to an end after months of delays.

The project at Euclid Crescent, which was scheduled for completion in August, has overrun due to labour and materials shortages.

The 200-year-old cobbled road, which runs from Albert Square past Dundee High School, has been upgraded with specialist granite setts and flagstones.

Councillor Kevin Keenan said that if a similar setback occurred on a busier street, it could have been “horrendous”.

But the Labour group leader says avoiding an even greater bill is some consolatio­n.

He said: “Imagine a roadworks project overran by that much on a very busy stretch, it would be horrendous.

“The amount of extra pollution and congestion that occurs when traffic is diverted during these projects can be really bad. It’s a very high cost in this case, but these things sometimes do have a high price. There’s no getting away from that.

“So long as the overrun has not cost much more than was originally estimated, then it is what it is.”

One worker who uses the nearby bus stops said: “It has been inconvenie­nt with the road completely closed at times, as it’s a handy shortcut up past the university.

“It feels like it’s been going on for years.

“The new stones do look nice, but I am shocked to hear that cost it seems a lot of money to be spending on a street that doesn’t have a lot of traffic on it.”

Euclid Crescent was once one of Dundee’s busiest thoroughfa­res and saw heavy use in the 1800s and the first half of the 20th Century.

It reopened at the end of November. However, workers have remained on site into December to finish off the full upgrade.

As well as labour and material issues, the delay has been put down to ducting to futureproo­f the street, which was added after the project start date.

It also required interactio­n with cellars in three separate buildings, including DC Thomson’s headquarte­rs at Meadowside.

Dundee City Council says the tender costs for the project was £665k, with the current costs estimated at £646k.

It was funded through Dundee City Council’s road maintenanc­e partnershi­p budget for financial year 2020-21 and 2021-22.

There was also external funding from Scottish Government’s Historic Town Centre Fund.

A spokespers­on for Dundee City Council said: “As well as the ongoing restrictio­ns placed on the way contractor­s were able to work, the additional programme duration was accounted for by labour shortages, issues obtaining necessary materials due to shortages, ducting to futureproo­f the street, which was added after the project start date and interactio­n with cellars in three separate buildings including DC Thomson’s headquarte­rs.”

 ?? ?? The work to resurface Euclid Crescent is now in the final stretch after months of delay.
The work to resurface Euclid Crescent is now in the final stretch after months of delay.

Newspapers in English

Newspapers from United Kingdom