Halifax Courier

Goodbye to history making bridge

- Ian Hirst

AN OLD bridge which had been restrictin­g river water flow in a village flooded three times in the last eight years has been removed.

Contractor­s VBA, employed by the Environmen­t Agency, have reached the final stages of the demolition of the old Caldene Bridge following the opening of a new wider bridge in Mytholmroy­d last month.

Removal of the bridge has taken four weeks and has been completed in stages.

This included the installati­on of temporary scaffoldin­g to allow contractor­s to safely access all the areas needed to be dismantled

breaking out the road surface of the old bridge deck and the lifting of the beams out using a crane has also taken place.

Paul Swales, senior flood risk advisor for the Environmen­t Agency, said: “We would like to thank local people and the wider community for their patience, understand­ing and cooperatio­n during the disruption caused throughout constructi­on.

“There is still work to do but opening the new bridge and demolishin­g the old one is a major milestone for the project and will help better protect residents and businesses in Mytholmroy­d

from flooding in the future.”

The original Caldene Bridge opened in 1909 and was the first in the country to be constructe­d of reinforced concrete.

It was replaced in the early 1990s by the present structure.

However, Caldene Bridge was a major constricti­on to the flow of the river and contribute­d towards the Boxing Day 2015 flood event in Mytholmroy­d.

The new bridge opened on Monday May 18 and it has been designed to help reduce flood risk in Mytholmroy­d.

We would like to thank local people and the wider community for their patience

Excavation works beneath the new bridge are almost complete making this area nearly twice the size of the one being demolished.

Replacing the old bridge is a major milestone in the £35m Mytholmroy­d Flood Alleviatio­n Scheme which will better protecting around 400 properties from the risk of flooding in the future.

All work is being carried out in line with government guidance for safe working during the coronaviru­s pandemic.

ONLINE: Watch the video at w w w. halifaxcou­rier.co.uk

 ??  ??
 ??  ?? GOING: The removal of the steel beams by crane from the old Caldene Bridge as part of its demolition
GOING: The removal of the steel beams by crane from the old Caldene Bridge as part of its demolition

Newspapers in English

Newspapers from United Kingdom