PROJECT TIMELINE
Plot purchased February 2016
Planning application submitted April 2016 Planning permission approved July 2016 Start on site (site clearing) July 2016 Foundations completed 28 November 2016 Watertight shell Mid February 2016 Windows installed End of March 2017 First fix March 2017
Second fix August 2017
Final decoration October 2017
Date occupied 4 November 2017