Rail (UK)

Delay for EGIP

- Richard Clinnick Assistant Editor richard.clinnick@bauermedia.co.uk @Clinnick1

Seven-month delay to Edinburgh-Glasgow project means electric trains will not be running until July 2017.

SCOTTISH Government has reacted angrily to seven-month delays to the Edinburgh-Glasgow Improvemen­t Programme (EGIP), which means electric trains will be running in July 2017 rather than December 2016.

The delay, revealed in the Office of Rail and Road’s’ Network Rail Monitor covering October 18 2015 to March 31 2016, has been caused by “extra compliance requiremen­ts, complicate­d interfaces with other projects, and other unforeseen factors such as severe weather impacts”, said Phil Verster, Managing Director of Network Rail Scotland and the ScotRail Alliance.

Scottish Transport Minister Humza Yousaf said he was “very concerned and disappoint­ed” about NR’s latest programme assessment for Scotland.

“Network Rail has informed Transport Scotland that the Edinburgh-Glasgow line will not be running electric services until July 2017. This is seven months later than scheduled and seven months later than they advised ministers two months ago,” he said.

“This will also increase the cost of the project beyond the previous £742 million estimate. Network Rail’s cost estimates for a number of other major projects that are at earlier stages of delivery have also increased. Moreover, progress on other projects has also been slower than expected.

“I am not prepared to simply accept the long-term cost implicatio­ns, nor the revised programmes that Network Rail has set out. I will also be doing everything possible to ensure that Network Rail delivers the full programme in Scotland by March 2019 and without any extra funding from the Scottish Government.”

Yousaf said that while there is always risk with delivery of major constructi­on projects, he said NR had fallen short of previous standards. He highlighte­d the Borders Railway as a project it got right, and said EGIP was an example of poor management of contractor­s.

“Across the programme there are systemic issues including poor planning and cost estimation and a failure to properly incorporat­e well establishe­d regulation­s into their project plans,” he said.

He confirmed, however, that the introducti­on of the Class 385s on EGIP was still planned for September 2017.

Yousaf recognised that ORR had identified weaknesses in NR’s’ project delivery, and also that NR was taking steps to remedy these. But he said he intended to go deeper into the problems and seek assurances regarding delivery.

Transport Scotland officials have been tasked with undertakin­g a review of the NR programme, and the Scottish Futures Trust will provide additional assurance. The governance structures for the delivery of major rail projects will also be reviewed. He said this will be completed by September, at which point Yousaf plans to take senior NR officials before the Rural Economy and Connectivi­ty Committee to set out how they intend to deliver promised improvemen­ts, the costs and what is being done to address concerns raised by Scottish Government and ORR.

Verster said: “Very importantl­y, our teams have learned valuable

lessons from the circumstan­ces, decisions and programme impacts over the last months.”

He said EGIP “is still progressin­g well”, and that NR was still committed to delivering the overall railway enhancemen­t in Scotland by March 2019 within the agreed funding limits.

Karl Budge, director for Network Rail Investment Projects in Scotland, said: “We are delivering a hugely exciting and hugely ambitious enhancemen­t programme in Scotland. We have strengthen­ed our delivery structure, creating a new management team and changing how we manage the programme, supply chain and contractor­s. This new structure will improve our decision-making processes.

“We are working with Transport Scotland to deliver our enhancemen­t programme as quickly and cost-effectivel­y as possible for both the taxpayer and passenger.”

In the Monitor, the ORR writes: “Some aspects of EGIP are progressin­g to plan, including the new station at Edinburgh Gateway.” It highlights the “significan­t challenges” to the delivery of Key Output 1 obligation for EGIP, which is the introducti­on of electric services in December 2016 ahead of the overall KO1 milestone of March 2017, as “the need for Network Rail to demonstrat­e infrastruc­ture compliance with relevant internatio­nal engineerin­g specificat­ions and its obligation­s under the Electricit­y at Work Regulation­s 1989”.

It further states: “In the CP5 [Control Period 5, 2014-19] Final Determinat­ion we establishe­d an assumed efficient price for EGIP of £490m. Estimated costs have since risen, in large part due to the additional compliance scope requiremen­ts, the complicate­d interface with Buchanan Galleries project, and additional line speed works to achieve journey time improvemen­ts.”

 ??  ??
 ??  ??

Newspapers in English

Newspapers from United Kingdom