Rail (UK)

Invisible investment

PAUL STEPHEN scratches beneath the surface of Network Rail’s work on the southeaste­rn end of the Elizabeth Line and discovers that the money being spent now will bring benefits for decades to come

-

RAIL scratches beneath the surface of Network Rail’s work on Crossrail’s southeaste­rn arm at Abbey Wood.

Apart from the 26 miles of tunnels constructe­d by Crossrail Ltd beneath central London, Network Rail is responsibl­e for delivering £ 2.3 billion worth of work above ground, where the Crossrail route utilises parts of the existing network.

This includes modifying 28 existing stations, and is largely concentrat­ed on enhancing the Great Eastern Main Line between Liverpool Street and Shenfield, and the Great Western Main Line between Paddington and Heathrow Junction and Reading.

It also includes upgrading a much shorter section of track on Crossrail’s south-eastern arm, however, running alongside the North Kent Line from the Plumstead eastern tunnel portal to Abbey Wood, where a new terminus station is being built for Crossrail, to act as an interchang­e with Southeaste­rn’s existing through services.

Work began in 2013 and is rapidly nearing completion, on what is effectivel­y a threemile constructi­on site in preparatio­n of the first Elizabeth Line services, which will run on this section in December 2018.

For two miles to the west of Abbey Wood station, the two-track formation of the North Kent Line needed to be widened into a fourtrack corridor to accommodat­e the two new Crossrail tracks, emerging from Plumstead tunnel.

To create sufficient space, the North Kent Line tracks had to be moved five to six metres further south for a distance of two miles, and then gradually slewed from their new positions to reconnect with the old alignment, approximat­ely a mile to the east of Abbey Wood station.

The task of widening the alignment was complicate­d by the high water table of the surroundin­g land, which used to be marshland until it was drained and then urbanised by Victorian developers during the 19th century.

NR’s solution was to drive 1,800 concrete piles up to nine metres into the ground, to support wide concrete ballast slabs, placed on either side of former two-track alignment.

This was expensive as well as challengin­g, and almost three quarters of the £150 million budget spent by Network Rail on this section of Crossrail was invested in building these earthworks and drainage courses.

Finding adequate room for four tracks was also problemati­c for NR’s engineers, requiring the demolition of several endof-terrace properties and the compulsory purchase of some sections of adjoining gardens.

“The single biggest challenge has been

The single biggest challenge has been building this through a housing estate. Peter Hume, Senior Programme Manager, Network Rail

building this through a housing estate,” explains Network Rail’s senior programme manager Peter Hume. “There are 2,000 residences that encircle a site over three miles long.

“You can’t see where a huge amount of our investment has gone, as it’s been done below ground level to solve that drainage problem.”

The project also required a great deal of logistical planning. Trackwork had to be carefully carried out in phases, in order to support the early establishm­ent of a railhead and temporary logistics centre at Plumstead tunnel portal for engineerin­g trains, used for the ongoing fit-out of the tunnels and stations by Crossrail contractor ATC.

This end of the three-mile worksite was, therefore, completed first, so that ATC could stable its concreting factory train at Plumstead, and an overhead gantry crane could be erected above sidings to supply engineerin­g trains used for trackwork, and all other necessary works, some of which are ongoing.

A £ 30m permanent depot will eventually be built here for maintenanc­e rail vehicles, which will be operationa­l in early 2019.

It was also important to conduct the work in stages in order to keep Abbey Wood open, a station used by some 4,500 people during the morning peak.

With the North Kent lines moved south, both of Abbey Wood’s original two platforms have been demolished and rebuilt, to form two new island platforms.

The southernmo­st of these was completed first, and a temporary station building erected so that Southeaste­rn services could continue to serve the station while work

What’s been carried out here has been so extensive that no further work should be necessary for at least 20 years. Peter Hume, Senior Programme Manager, Network Rail

began on the northern island platform, and the new station building itself, which is elevated above all four running lines.

Disruption has therefore been kept to a minimum, adds Hume, apart from a series of brief full-line possession­s, an unavoidabl­e measure due to the close proximity of fully energised 700V DC lines to the building works. The scope of the trackwork means that future enhancemen­t and renewal work should be kept to a minimum, however, limiting the need for any future possession­s.

“The project has taken four years. We could have shut the station completely and diverted Southeaste­rn trains to do it faster, but the industry view was that Abbey Wood is too busy to close. To get round that we developed a strategy using convention­al line possession­s that allowed people to carry on travelling, and with minimal impact.

“100% of the railway assets have been replaced. What’s been carried out here has been so extensive that no further work should be necessary for at least 20 years. This section of track will be maintenanc­e and renewal free for a long time.”

The station design itself had to cater for up to 20,000 people using Abbey Wood in the morning peak, with half of those interchang­ing to Elizabeth Line services, and the rest consisting of local journeys.

Due to the local drainage problems, a further £ 20m had to be spent on building the extensive foundation­s and concrete support structure required beneath the elevated concourse, while £ 25m is being spent on the concourse itself. The primary contractor on-site leading all the works is Balfour Beatty.

The station’s distinguis­hing feature is a gently curving roof shaped like a manta ray, formed by glulam (glued manufactur­ed timber) wood panels installed by Austrian firm Wiehag, that are covered in zinc. Beneath the roof, the station building has been constructe­d using 31 tonnes of steel beams and girders.

It makes a bold architectu­ral statement, but the new station has also been designed to deliver more functional improvemen­ts to the economical­ly depressed local area, via its integratio­n with adjacent flyover, Harrow Manorway (the A2041).

This elevated road has made walking

around the area difficult, and has formed a visually intrusive physical barrier through the area since its constructi­on in 1975.

New staircases, walkways and a granitepav­ed concourse will dramatical­ly enhance pedestrian access between the areas of Thamesmead and Bexleyheat­h located on opposite sides of the railway, while stimulatin­g more than £10m investment from local councils on improvemen­ts to the surroundin­g urban area.

It has also had a regenerati­ve effect on Abbey Wood, with a new supermarke­t already opening close to the station, and 1,500 homes under constructi­on nearby. Meanwhile, planning permission has been granted for a public plaza, library and a further 220 new homes.

The new concourse will also contain retail units to closely resemble a high street, reinforcin­g the station environmen­t’s feel as a thoroughfa­re linking the two communitie­s.

Now that the external structure is complete, the emphasis will shift onto the station building’s internal fit-out, before it is ready to open to Southeaste­rn customers in October.

That month will also mark the end of Network Rail’s involvemen­t in the project, as the Crossrail island platform and running lines are handed over to Crossrail Ltd to begin dynamic testing and commission­ing, in advance of the full station opening in December 2018.

Matt Steele, Crossrail Programme Director at Network Rail, concludes: “This is one of my favourite sites as it’s an opportunit­y to leave something iconic and make a bold architectu­ral statement. It’s also a rare chance to build some all-new railway.”

 ?? PAUL STEPHEN. PAUL STEPHEN. PAUL STEPHEN. ?? A Down Southeaste­rn service occupies Platform 2 at Abbey Wood on March 24, demonstrat­ing the close proximity of the fully energised North Kent running lines to the island platform constructe­d for Crossrail to the right. The Crossrail tracks were due to...
PAUL STEPHEN. PAUL STEPHEN. PAUL STEPHEN. A Down Southeaste­rn service occupies Platform 2 at Abbey Wood on March 24, demonstrat­ing the close proximity of the fully energised North Kent running lines to the island platform constructe­d for Crossrail to the right. The Crossrail tracks were due to...
 ?? CROSSRAIL. ?? An aerial shot of Abbey Wood station, showing where a level crossing was once situated in the area beneath the white roof of the new station, until being replaced by the flyover in the far right of the shot in 1975. Network Rail encountere­d an...
CROSSRAIL. An aerial shot of Abbey Wood station, showing where a level crossing was once situated in the area beneath the white roof of the new station, until being replaced by the flyover in the far right of the shot in 1975. Network Rail encountere­d an...
 ??  ??
 ?? PAUL STEPHEN. NETWORK RAIL. ?? The view at concourse level on March 24, prior to interior fit-out. The main timber roof beams are 45 metres long, which is the equivalent of four London buses end to end. The new concourse measures 1,500m2 (the size of six tennis courts). Abbey Wood...
PAUL STEPHEN. NETWORK RAIL. The view at concourse level on March 24, prior to interior fit-out. The main timber roof beams are 45 metres long, which is the equivalent of four London buses end to end. The new concourse measures 1,500m2 (the size of six tennis courts). Abbey Wood...

Newspapers in English

Newspapers from United Kingdom