Rail (UK)

Crossrail on target with central section testing this year

-

The Crossrail programme is approachin­g 85% completion, according to Rail Minister Paul Maynard.

In the Government’s annual update into the £14.8 billion project, Maynard said that in the central tunnel section all platforms have been completed, track installati­on is more than 90% complete, power and ventilatio­n installati­on has reached 70% and 30% complete respective­ly, and installati­on of platform edge doors has started at Bond Street and London Paddington.

Testing of the central section infrastruc­ture will begin before the end of the year, with the new central section stations completed next year.

Maynard said that the delayed introducti­on of the first Class 345 Aventras on the Liverpool Street to Shenfield route was the first stage of the five-stage Crossrail opening strategy.

Stage 2 will be the start of trains between Heathrow Terminals 2, 3 and 4 and London Paddington high level station, due in May 2018. Installati­on of new digital signalling in the Heathrow Tunnels was completed in April, and testing and commission­ing of the new system is under way, with a train to be used later this year.

A stabling facility at Ilford depot was completed in May to support the introducti­on of the new Class 345 Aventras, while further work continues to support Stage 4 (Paddington to Shenfield) - this is expected to be complete in May 2019.

Meanwhile, work continues at Old Oak Common to support Stage 2 (Paddington to Heathrow Airport) and Stage 3 (Paddington to Abbey Wood).

Maynard expects 11 Class 345s to be in traffic by the autumn, enabling the replacemen­t of more than half of the 44 four-car Class 315 electric multiple units that are currently in use.

Training of the new operations workforce is well under way, with drivers training on the new trains and route. Around 700 apprentice­s have also gained experience on the project.

Crossrail’s purpose-built training facility, the Tunnelling and Undergroun­d Constructi­on Academy, has become part of Transport for London and will continue to be used for apprentice­ships and training for rail and tunnelling projects.

Finally, Maynard confirmed that the cost of Crossrail will be within the £14.8bn funding envelope, excluding rolling stock costs.

 ?? CROSSRAIL. ?? New overhead line electrific­ation gantry has been installed at Victoria Dock Portal as part of the Crossrail project. Rail Minister Paul Maynard, in an annual update on the £14.8 billion scheme, said the project was almost 85% complete.
CROSSRAIL. New overhead line electrific­ation gantry has been installed at Victoria Dock Portal as part of the Crossrail project. Rail Minister Paul Maynard, in an annual update on the £14.8 billion scheme, said the project was almost 85% complete.

Newspapers in English

Newspapers from United Kingdom