Rail (UK)

London Bridge

-

Network Rail says there have been no service-affecting infrastruc­ture failures since the penultimat­e phase of the London Bridge remodellin­g was completed on August 28, with the Public Performanc­e Measure (PPM) of trains running through the station at 95%.

Speaking exclusivel­y to RAIL, Network Rail Project Director, Thameslink Railway Systems Mark Somers said the latest works - which included bringing lines 6/7 back into use - have provided much more flexibilit­y to Down Charing Cross services, with trains able to use alternate platforms. This has meant that trains are not now waiting for clear platforms at London Bridge.

Tracks on the Bermondsey diveunder have now been completed, with two new lines brought into service at the commission­ing. This allows attention to turn to completion of the remaining signalling installati­on works and pre-testing, ahead of the final Christmas blockade.

Lines 3 and 4, which formerly served Charing Cross services, have been taken out of use to make the final connection­s to the Bermondsey flyover. And the tracks for Platforms 3 and 4, which are designated for Thameslink services, are now under constructi­on.

The station remodellin­g is believed to be among the biggest ever undertaken in Britain. The final phase will involve commission­ing Platforms 1-5, opening the remainder of the new concourse, and commission­ing new signalling (including European Train Control System Level 2). This will take place between December 23 2017 and January 1 2018.

During the Christmas blockade, two crossovers at Blackfriar­s will be taken out and new ones made operationa­l, along with

reconnecti­on to the Spur lines running round to Charing Cross and London Bridge - providing greater flexibilit­y in operations throughout this area.

Somers said the biggest task will be to bring hundreds of new signalling assets into use. To achieve this, many of these will be tested and correspond­ed to the Three Bridges Rail Operating Centre before the blockade starts.

In the final 24-36 hours of the blockade, the signalling sections and track layout will be proved and test trains will run through the area, including Class 700s to prove the ETCS installati­on. Trains will be diverted - many to London Victoria and some to the former Internatio­nal platforms at Waterloo.

By the time work is completed, more than 25 miles of tracks will have been relaid on the approaches to London Bridge, and about 150 switches and crossing units installed. Particular attention has been paid to the resilience of signalling systems, with much equipment traditiona­lly located on the trackside relocated to make it easier to access and maintain.

Several signalling innovation­s are being introduced to improve service reliabilit­y through the area. The first is Proceed on Sight Aspect, a signal aspect for use during lineside signalling failures which instructs drivers to enter a signal section.

Newspapers in English

Newspapers from United Kingdom