Rail (UK)

Bank Holiday engineerin­g works

-

Network Rail says the majority of its August Bank Holiday engineerin­g works on August 26-28 were completed on time, with an extensive programme on the West Coast Main Line in particular.

While there were technical difficulti­es at London Waterloo ( RAIL 835), High Speed 2 preparatio­n works at London Euston were finished on time. These involved re-routing a major power supply to the station to allow further preparator­y works to take place.

Elsewhere on the WCML, track renewals between Hemel Hempstead and Berkhamste­d were completed, as were renewals near Watford. Drainage was upgraded at Primrose Hill, and extensive tamping works took place at Bletchley.

On the Great Eastern Main Line, 1km of overhead catenary was replaced at Brentwood, and preparator­y works for catenary replacemen­t were completed at Ilford and Manor Park. At Pudding Mill Lane (Stratford), 200 metres of track was installed to prepare for the connection of Crossrail to the main line.

On the Chase line between Rugeley Trent Valley and Walsall, upgrade works continued, with the route handed back on August 29 following its closure from August 13.

Track was replaced and realigned at various locations on the route, piling for the remaining overhead line electrific­ation stanchions was installed, stanchions and gantries were installed elsewhere, and Bloxwich level crossing and Landywood and Stoneyfiel­ds footpath crossings were closed.

Newspapers in English

Newspapers from United Kingdom