Rail (UK)

Right place, right time

The dysfunctio­nal interface between railways was further hindered by a tangled mess of regulation­s - until a collaborat­ion project took the bull by the horns, writes RICHARD CLINNICK

-

The East London Line opened in 2010. It operates over part of the former London Undergroun­d network, and links the former Southern Region at New Cross Gate with the North London Line at Highbury & Islington, running along part of the railway that once served Broad Street, until it closed in 1986.

Carrying trains delivered in 200811, the ELL is part of the LO network, and on the section north of New Cross Gate it is purely Transport for London infrastruc­ture. Network Rail is responsibl­e for the infrastruc­ture shared by Govia Thameslink Railway, and on the NLL, but in between is TfL. Trains operated by LO were being delayed by trains operating on NR infrastruc­ture, which delayed their arrival onto the core section of the ELL.

The problem centred on the dependence on the Sydenham corridor to deliver trains into the core ELL section on time. This had a negative impact on ELL performanc­e, and it was clear that changes were needed.

With the introducti­on of a new concession operator for London Overground, there was an opportunit­y to introduce new ideas and new ways of working, in a programme aimed at getting the line’s trains to run on time. However, improving reliabilit­y was not that simple. It required collaborat­ion from three key stakeholde­rs, changes in the way of working, and a rethink of train regulation policy. And it would have to be done quickly, to minimise delays.

The ‘Right Time Right Pathway’ trial was implemente­d. Not only did it have the potential to improve punctualit­y and performanc­e, but by simplifyin­g the various processes, it improved safety by reducing the likelihood of human error. Unlike similar trials, this was carried out on a complex section of railway.

Legacy regulation policies had become increasing­ly complicate­d, with amendments made over time purely on an ad hoc basis. This had, in turn, created sub-optimal outcomes for punctualit­y on the East London Line as trains were arriving at the core late. Arriva Rail London, which took over the concession in November last year, says that the policies had evolved into a complex operating environmen­t for signallers. And because the railway is so heavily used in this section, the fear of unintended and catastroph­ic side-effects of any change had hampered progress. The project team in charge of the trial overcame these fears through the introducti­on of a collaborat­ive and consultati­ve approach from the very start of the trial, and that became the key to winning the support of all those involved.

ARL collaborat­ed with both GTR and NR to adopt a project management approach that was built on cross-industry consultati­on and early engagement with signallers in order to set up the trial. While the trial was running, existing regulation policies were suspended in favour of the new method.

LONG-TERM BENEFITS FOR RAIL

The ‘Right Time Right Pathway’ trial has potential long-term benefits, not just in and around London, but for the rail industry as a whole.

It’s believed that an industry leading train regulation policy approach could set the railway on the path to being a ‘right time railway’ in Control Period 6 (April 1 2019-March 31 2024). It could deliver significan­t safety benefits by ensuring that intervals are maintained, which in turn means that capacity can be planned and managed, and overcrowdi­ng can be reduced. The implementa­tion of the methodolog­y across the industry could also deliver value for money for rail and for passengers as, according to the National Rail Awards submission, “a right time railway will have greater opportunit­ies to reinvest incentive bonuses into making future performanc­e and reliabilit­y improvemen­ts.”

Two members of ARL operationa­l staff were seconded to NR, so the latter could gain valuable operator insight and experience. In these roles, the seconded staff acted on behalf of NR.

The trial itself involved the creation of a revised train regulation policy at specific locations on the ELL where both operators ran trains. The idea was to see if changes could be made to improve performanc­e and simplify regulation decisions that needed to be made by signallers.

The trial took place during Railway Period 12, which ran for four weeks starting on February 6 this year. The project team agreed that a set of success criteria should be identified. This included a 50% reduction in operator-on-operator Public Performanc­e Measuremen­t (PPM) failures and a 50% reduction in regulation-attributed incidents within the trial areas, as well as no significan­t issues being raised at a Post Implementa­tion Review.

The results showed a 5.7% uplift in train punctualit­y on the ELL, with a rise from 80.92% in Period 11 (2016-2017) to 85.52% in Period 12 (2016-2017). This, ARL

The entry represents true collaborat­ion, cutting across the commercial and contractua­l interests of the different parties involved. NRA Panel

says, showed a period of sustained and continuous improvemen­t as a “direct result of the ‘Right Time Right Pathway’ regulation policy introduced by the trial. At the time of entry submission for the National Rail Awards, ARL reports that it had recorded the best ever punctualit­y on a weekday for the ELL of 92.76%.

The post-trial review highlighte­d, among other things, that the success criteria was achieved, that the signallers were involved from the outset and that their views were listened to. The latter has also reported that they like the fact the process has simplified train regulation policies, which in turn helps them regulate trains, and that these decisions are reflected in improved performanc­e.

What this shows, says ARL, is the impact of what can be achieved through the implementa­tion of collaborat­ive crossindus­try partnershi­ps. There was a hugely positive reaction from all organisati­ons involved and an agreement to convert the trial to a permanent change.

The project has also created opportunit­ies for ARL, GTR and NR to transfer what has been learned from this trial to other parts of the rail network, with ARL looking to implement similar methods of working onto the West Anglia route, while GTR is using what it has learned to “bring benefit to the preparatio­n of upcoming timetable changes on Thameslink”. This will be in regards to the need for trains on the TL core section to arrive on time, and ready to pass through that section.

This project has deservedly been given the National Rail Awards Teamwork of the Year accolade. It identified and challenged a perceived weakness in the industry and delivered much-needed improvemen­t to such an extent that Network Rail is considerin­g widening the geographic­al scope of the ‘Right Time Right Pathway’ train regulation policy, and also to use the process to test modified train regulation policies on other NR routes. That is to be applauded.

 ?? NETWORK RAIL. ?? A workstatio­n at Three Bridges Rail Operating Centre, where the junctions between Transport for London and Network Rail infrastruc­ture are controlled.
NETWORK RAIL. A workstatio­n at Three Bridges Rail Operating Centre, where the junctions between Transport for London and Network Rail infrastruc­ture are controlled.
 ??  ??

Newspapers in English

Newspapers from United Kingdom