Rail (UK)

Extra London Bridge work pushes up Thameslink cost

- Richard Clinnick Assistant Editor richard.clinnick@bauermedia.co.uk @Clinnick1

COSTS on the Thameslink project have risen by £474 million from the 2012 budget, according to the latest National Audit Office (NAO) report into the project.

The overall cost of the scheme is £5.5 billion. Phase 2’s budget has increased by 18% from £2,629m to £3,103m.

The NAO says this is largely due to associated work at London Bridge, with an extra £210m required after it was determined that the station and railway system designs were inappropri­ate for the site. Some changes involved extra infrastruc­ture work, while some existing station assets were found to be in a poorer condition than anticipate­d. Design costs added a further £60m, due to the volume of the changes.

Accelerati­ng the programme cost £109m, involving constructi­on and procuremen­t in order to meet deadlines. The cancellati­on of a national traffic management system cost £66m, while constructi­on inflation cost £29m.

Thameslink has been split into two phases. Phase 1, including the redevelopm­ent of Blackfriar­s and Farringdon stations, was completed on time and on budget in 2011 for £2.4bn. Phase 2 started in 2013 and includes the London Bridge redevelopm­ent and introducti­on of Automatic Train Operation (ATO). Its budget is £3.1bn.

NAO said that as Network Rail developed its detailed design for

London Bridge and accessed the site, so it found conditions were not what was expected. This meant changes to the design, additional work, and accelerati­on of other works to meet schedules. NR was not set up to deal with the scale of the changes, according to NAO.

Released on November 23, the NAO report states that while NR has kept the infrastruc­ture works to schedule, failing to complete planned work could set the project back by up to a year, because of the sequence in which the work needs to be done. It states NR has so far avoided a delay and has only one more set of critical works planned - this Christmas.

Responding to the NAO report, an NR spokesman said: “The Thameslink Programme is transformi­ng north-south travel through London to provide more frequent, more reliable journeys to new destinatio­ns for passengers, and upgraded stations including the landmark, entirely redevelope­d London Bridge.

“On January 2, the final section of the brand new, modern concourse - which is larger than the pitch at Wembley - will open to passengers alongside entirely rebuilt Platforms 1-5. Thousands of new, more frequent services to more destinatio­ns than ever before will be introduced throughout 2018, to deliver better journeys for the millions of passengers who travel on this route each year.”

Linda McCord, passenger manager at independen­t watchdog Transport Focus, said: “Passengers using Thameslink services will be pleased to hear that an improved service is on its way. We called for the timetable changes to be phased in, and are pleased to see the operator has taken this sensible approach, hopefully allowing passengers to experience the benefits while minimising the chances of further disruption.”

 ??  ??
 ??  ??
 ?? ALEX DASI-SUTTON. ?? Govia Thameslink Railway 700001 leaves Norwood Junction on November 25, with the 0840 Bedford-Brighton. The ‘700s’ were ordered for the Thameslink scheme, and were introduced some three months late. Costs of the overall TL project have risen, largely...
ALEX DASI-SUTTON. Govia Thameslink Railway 700001 leaves Norwood Junction on November 25, with the 0840 Bedford-Brighton. The ‘700s’ were ordered for the Thameslink scheme, and were introduced some three months late. Costs of the overall TL project have risen, largely...
 ??  ??

Newspapers in English

Newspapers from United Kingdom