Rail (UK)

DEFINING CORE COMPETENCY

Network Rail’s Thameslink Programme Director SIMON BLANCHFLOW­ER delivers a progress report on NR’s collaborat­ive work with Siemens to switch from convention­al to in-cab signalling on Thameslink’s central section

-

On May 20, the introducti­on of higher-frequency Thameslink services through central London commenced, to serve a wider range of destinatio­ns including Peterborou­gh, Ashford and Cambridge.

Despite a number of well-publicised operationa­l difficulti­es in implementi­ng the timetable change, 18 trains per hour (tph) are now scheduled to travel in each direction at peak times through the Thameslink ‘core’ between St Pancras Internatio­nal and Blackfriar­s.

This figure will rise incrementa­lly with the aim to eventually move to 24 trains per hour or a train every two to three minutes.

Underpinni­ng this uplifted central core frequency has been the installati­on of ATO (Automatic Train Operation) and ETCS (European Train Control System) Level 2 digital in-cab signalling technology designed and supplied by Siemens, and the introducti­on of Siemens’ National Rail Awards-winning fleet of Class 700s ( RAIL 862).

ETCS Level 2 facilitate­s an increase in the number of available train paths compared with convention­al signalling, by having much shorter track circuit block sections. This reduces headways by enabling trains to run much closer together. Alongside ETCS, existing lineside signals are being retained throughout the core for non-ETCS-fitted trains (also providing extra resilience in the unlikely event of equipment failure).

Starting next year a traffic management system will be progressiv­ely rolled out across a wider area than the core (approximat­ely 20 minutes’ travel time in all directions), to help keep performanc­e as close as possible to the timetabled path of each train, and to mitigate the risk of late-running services.

This complex and technicall­y challengin­g project delivered a UK ‘first’ on March 17 this year, when the first main line train ever to use ETCS and ATO while in passenger traffic travelled through the core.

This historic moment was the latest step in an extensive and highly collaborat­ive testing programme between engineers from Siemens, Govia Thameslink Railway and Network Rail that had begun five year earlier, following the opening of a purpose-built system integratio­n laboratory at James Forbes House (near Blackfriar­s station), where NR’s Thameslink Programme High Capacity Infrastruc­ture Team was then based.

The facility was visited by RAIL in February ( RAIL 848). It contains an exact replica of a Class 700 cab and at least one example of each component needed to run ETCS and ATO - including a dummy balise (ETCS transponde­r), GSM-R connection, plus real trackside interlocki­ngs and a radio block controller.

The lab enables the offline testing of ETCS and ATO technology using real equipment and the ‘700’ simulator. It has the capacity to simulate 60 trains, and to operate any one of them in order to replicate the connection that trains will have with other equipped trains in the core. It remains in use while software continues to be optimised, while a further use is actively being sought for it following the end of the Thameslink Programme next year.

Dynamic testing began at NR’s ETCS National Integratio­n Facility at Hitchin in 2014, before switching to overnight testing on the core itself in April 2016, using a Class 700 train

specifical­ly provided for this purpose by GTR.

The equipment went live on Thameslink earlier this year and is now fully functional, although almost all Thameslink services will remain convention­ally signalled for the immediate future. For the present time, GTR will continue to focus on training its driver managers and competence developmen­t managers on the two Class 700s (700019/110) that have temporaril­y been withdrawn from service for training and testing purposes.

Siemens and NR have also taken advantage of the necessary time required to implement full driver training to use these trains to further optimise the software, and to build a track database of the many crossovers and platforms in the central section through which trains could be routed.

“The ‘700’ is clearly still a new train and mileage is progressiv­ely accruing, but in terms of technology integratio­n all this testing has proven that everything [from concept] works in reality,” says NR’s Thameslink Programme Director Simon Blanchflow­er.

“Testing is still ongoing because while ATO and ETCS has been proven in the core, we now have to extend it from Blackfriar­s round to London Bridge and then integrate it with the rolling stock. This shows that we’re not standing still with this system, but developing it further. It is exciting times in terms of technology deployment.”

Once installati­on of trackside equipment is extended from just south of Blackfriar­s stations through to London Bridge, Siemens, GTR and Network Rail will once more collaborat­e for a testing phase in early 2019, before safety approval is granted by the Office for Rail and Road for it to be switched on by Easter.

Blanchflow­er is keen to emphasise that although there have been problems implementi­ng the Thameslink timetable, it was (neverthele­ss) purely an operationa­l issue. He points out that the ETCS and ATO technology is performing well and has had few glitches, and could in fact support up to 24tph

Thingshave­gonewellon Thameslink­becauseoft­heworkwe didwithSie­mensveryea­rlyonin researchan­ddevelopme­nt. Simon Blanchflow­er, Thameslink Programme Director, Network Rail

by May 2019. The system is being tested to support up to 30tph, although this would be reserved for times of extreme disruption - in such an event, some services would probably be required to run non-stop, undoubtedl­y inconvenie­ncing some passengers.

However, the industry has agreed it would be beneficial to passengers to introduce the timetable over a longer period, to enable experience to be embedded between stages.

Blanchflow­er adds: “We’ve hit almost all of our [infrastruc­ture] targets and we’re working hard with our industry partners to build confidence around the reliabilit­y of future timetable uplifts to 24tph, and will support operators to deliver that capacity increase.

“Passengers will be well aware of the key challenge at the moment, however, which is to stabilise day-to-day performanc­e. Only when they are confident we’ve done that and cancellati­ons are withdrawn from the schedule, will they begin to see some of the very real benefits this technology offers.”

Looking ahead, Blanchflow­er is hopeful that many of the lessons learned from the Thameslink Programme are deployed to the first wave of Digital Railway projects, which are due to commence in Control Period 6 (April 2019-March 2024).

These include the installati­on of ETCS at Feltham and on the southern portion of the East Coast Main Line from Peterborou­gh to King’s Cross.

He says this demonstrat­es the immense value of selecting a technology supplier and project partner such as Siemens at the earliest possible stage of the design process, adding: “We continue to have interest from European railways and from further afield such as Australia who want to understand what we’ve achieved, and the methodolog­y we’ve used to get there, which we’re keen to share.

“Things have gone well on Thameslink because of the work we did with Siemens very early on in research and developmen­t, which has made the process more robust. A key learning for Digital Railway has to be to work collaborat­ively with an early developmen­t partner on overall system developmen­t.

“Expression­s of interest have gone out on the East Coast Main Line, and I think that following the Thameslink model will reap benefits in creating strong designs at an early stage. The work we’ve done with Siemens’ trains and signalling and GTR, and getting all these partners together early on, has clearly benefited the project.”

He concludes: “I’m very keen on that and I often talk to [NR’s Digital Railway MD] David Waboso, who has also put in a lot of effort on collaborat­ion with the supply chain. Undoubtedl­y the success of Thameslink will help breed confidence that DR can be delivered and give some momentum for the next three or four projects.”

 ?? PAUL STEPHEN. ?? The view from the cab of 700019 on September 17, while on a test run for ETCS and ATO. It is being held just 65 metres behind another train at Blackfriar­s in one of the Core’s shortest track circuit block sections.
PAUL STEPHEN. The view from the cab of 700019 on September 17, while on a test run for ETCS and ATO. It is being held just 65 metres behind another train at Blackfriar­s in one of the Core’s shortest track circuit block sections.
 ??  ??
 ?? ANTONY GUPPY. ?? Govia Thameslink Railway 700046 passes an ETCS track block marker at Farringdon on March 14. These services will remain convention­ally signalled while software optimisati­on continues and until driver training is complete.
ANTONY GUPPY. Govia Thameslink Railway 700046 passes an ETCS track block marker at Farringdon on March 14. These services will remain convention­ally signalled while software optimisati­on continues and until driver training is complete.
 ??  ??

Newspapers in English

Newspapers from United Kingdom