Merseyrail platform upgrades continue

-

The latest phases of Merseyrail’s station platform upgrades to accommodat­e its new Stadler trains started on February 2, with work focusing on Southport to Hall Road on February 2-10 and then Formby to Bank Hall on February 11-24.

In March, Phase 7 begins with platform alteration­s between Hooton and Rock Ferry between March 2 and 22 and from Hooton to Chester on March 25-April 2.

During the closures, Network Rail will replace a bridge in Bootle that crosses the Leeds-Liverpool Canal on February 18-22, followed by track maintenanc­e on the Southport line on February 17. During the March works, Network Rail will strengthen the footbridge at Bromboroug­h station during its closure.