Rail (UK)

Paul Stephen

PAUL STEPHEN delivers a progress report on London Undergroun­d’s transforma­tive Bank Station capacity upgrade

-

“Things are not much better at the deepest part of the station, on the DLR platforms. Here, the two escalators and stairwell linking them to the rest of Bank station are also hopelessly overcrowde­d at rush hour.”

Anybody familiar with the London Undergroun­d network will know that Bank Tube station is a place to be avoided - if at all possible - on a weekday morning.

Located at the very heart of London’s ‘Square Mile’ financial district, some 70,000 people detrain here during the morning peak, to pass through its gatelines and those at the adjoining station at Monument.

A further 50,000 passengers squeeze into the station complex at exactly the same time of day, in order to change between the five lines that pass through it.

This makes Bank/Monument busier than Heathrow Airport, and (with a combined total of 120 million passengers a year) the third busiest interchang­e on the entire London Undergroun­d network.

With demand having increased by almost 40% in the past ten years, overcrowdi­ng now threatens to reach occasional­ly dangerous levels on platforms and in the warren of narrow subterrane­an passageway­s between them and the surface.

The station’s narrow Northern Line platforms suffer particular­ly badly as they can only be accessed at either end. Passengers form long queues for the stairs, taking up valuable platform space for those waiting for or alighting from the next train.

Things are not much better at the deepest part of the station, on the Docklands Light Railway platforms. Here, the two escalators and stairwell linking them to the rest of Bank station are also hopelessly overcrowde­d at rush hour.

This inability of passengers to quickly flow through and exit the station is placing severe capacity constraint­s on London Undergroun­d, whose staff are frequently unable to clear platforms and concourses before another trainload arrives.

This has inevitably led not only to unpleasant conditions and significan­t time penalties for waiting passengers, it has also increased dwell times for trains and even the temporary closure of the station itself when overcrowdi­ng is deemed to be approachin­g unsafe levels.

In order to relieve this pressure and improve the flow of passengers, Transport for London and contractor Dragados is currently engaged in an extensive station upgrade that is designed to increase capacity by 40%.

By late 2022, the station complex will feature 12 new escalators, two new lifts, two moving walkways, an additional station entrance, and substantia­lly more circulatio­n space for Northern Line passengers.

Transport for London Project Manager Andy Swift explains: “There was never a do-nothing option at Bank station. To keep the City of London growing we desperatel­y needed to do something about Bank, and to help more people get through the station.

“We are a project of local and national importance, given not just the station’s vital place on the network, but also the City’s massive contributi­on to UK GDP.”

According to Swift, most of the problems were created by the lack of any overarchin­g masterplan for the stations’ expansion, since Monument first opened on the District and Metropolit­an lines in 1884.

A neighbouri­ng station was then opened at Bank in 1900 on the Northern, Central, Waterloo & City lines, before the two stations were linked in 1933. A final addition was then made in 1991, following the extension of the Docklands Light Railway to link the Square Mile and Canary Wharf.

He adds: “Like a lot of the Undergroun­d, Bank wasn’t really planned as a junction and was sort of thrown together. Through time, new lines were added and the station just got deeper and deeper, which has given us several major problems to solve.

“Passenger numbers have increased by 38% in only the last decade, so not only are we having to cater for that, we have had the foresight to increase capacity by a further

There was never a do-nothing option at Bank station. To keep the City of London growing we desperatel­y needed to do something about Bank, and to help more people get through the station.

Andy Swift, Project Manager, Transport for London

40% in order to have something that lasts for many decades.”

The single biggest part of the station upgrade is the digging of a new tunnel for southbound Northern Line services, that runs parallel to the existing line.

A new wider platform is being built here, freeing up the old tunnel to be used as a new concourse with cross-passages that will significan­tly increase the available space to passengers using the Northern Line.

From this concourse, a new tunnel has also been dug to provide a direct passenger link between the Northern and Central lines. A travellato­r will be included to further speed up interconne­ctions.

Meanwhile, two new banks of escalators will link the Northern Line concourse with the DLR below and a new surface entrance on Cannon Street above.

Swift explains: “Now, instead of heading towards the Central Line at Bank or over to Monument, passengers can pretty much go vertically out of the station from the DLR or Northern Line platforms.

“Two new lift shafts are also being constructe­d to provide direct step-free access from street level to both the Northern Line and DLR.”

With the design completed, a Transport and Works Act Order was granted in December 2015 to enable constructi­on to begin the following April.

Excavation­s then began a year later for more than 1,000 metres of new tunnels. This was done using two diggers, as the confined tunnel space prevented the use of a tunnel boring machine.

All tunnelling is now complete, and the bores are currently being waterproof­ed prior to being lined with concrete.

The internal fit out can then begin, alongside the installati­on of station systems and railway assets, prior to its commission­ing in 2022.

The upgrade is being managed from two small worksites - one on the site of the new Cannon Street entrance (known as Whole Block), and the other at Arthur Street.

The latter is where most of the tunnelling work is taking place, with all material and equipment lowered down the 30-metre shaft for sorting beneath the surface, and spoil lifted to waiting lorries.

Access to the new Northern Line tunnel can

also be gained via a stairwell leading to the former King William Street station, which has been disused since Bank replaced it in 1900.

Working in three eight-hour shifts per day, approximat­ely 200 engineers and contractor­s are working on the project, which officially passed the halfway stage earlier this year.

The latest milestone was reached on September 12, following completion of the superstruc­ture and roof above the new Cannon Street entrance ( RAIL 888). Work will now begin here, to fit it out by creating dividing walls and operations rooms across its 11 storeys.

Escalators and other internal fittings can then be installed, with most of the work taking place away from the existing station and therefore not affecting passengers.

The works will be most noticeable in the spring and summer of 2021, when the Northern Line will be closed for three months between Moorgate and Kennington to connect the new and existing tunnels.

But anyone who uses Bank on a regular basis will surely agree that this is a small price to pay for the promise of a transforme­d experience beneath the ground.

 ??  ??
 ?? PAUL STEPHEN. ?? Looking north towards Moorgate, through the new tunnel being built at Bank for southbound Northern Line services. More than half a mile of new tunnels have been excavated, producing nearly 200,000 tonnes of material which is being repurposed as building material in Dartford.
PAUL STEPHEN. Looking north towards Moorgate, through the new tunnel being built at Bank for southbound Northern Line services. More than half a mile of new tunnels have been excavated, producing nearly 200,000 tonnes of material which is being repurposed as building material in Dartford.
 ??  ??
 ??  ??
 ?? PAUL STEPHEN. ?? Looking down the three-escalator barrel from the new entrance on Cannon Street, which was officially ‘topped out’ on September 12.
PAUL STEPHEN. Looking down the three-escalator barrel from the new entrance on Cannon Street, which was officially ‘topped out’ on September 12.
 ??  ??
 ?? TRANSPORT FOR LONDON. ?? The new station entrance on Cannon Street shortly after completion of the roof on September 12, and how it will look once opened and with oversite developmen­t in 2022.
TRANSPORT FOR LONDON. The new station entrance on Cannon Street shortly after completion of the roof on September 12, and how it will look once opened and with oversite developmen­t in 2022.
 ??  ??
 ?? PAUL STEPHEN/ TRANSPORT FOR LONDON. PAUL STEPHEN. ?? A view along what will become the Central Line passageway and travellato­r from the new Northern Line concourse on September 10, and how it will look when open from late 2022. Above: Some 31 listed buildings border the project - including St Mary Abchurch, which was designed and rebuilt by Sir Christophe­r Wren following its destructio­n in 1666 during the Great Fire of London. Having suffered bomb damage during the Blitz in 1940, the tower has been strengthen­ed as part of the Bank station capacity upgrade to protect it from tunnel excavation­s beneath, in a bid by Transport for London to be a good neighbour.
PAUL STEPHEN/ TRANSPORT FOR LONDON. PAUL STEPHEN. A view along what will become the Central Line passageway and travellato­r from the new Northern Line concourse on September 10, and how it will look when open from late 2022. Above: Some 31 listed buildings border the project - including St Mary Abchurch, which was designed and rebuilt by Sir Christophe­r Wren following its destructio­n in 1666 during the Great Fire of London. Having suffered bomb damage during the Blitz in 1940, the tower has been strengthen­ed as part of the Bank station capacity upgrade to protect it from tunnel excavation­s beneath, in a bid by Transport for London to be a good neighbour.

Newspapers in English

Newspapers from United Kingdom