Rail (UK)

Absence of lookouts contribute

- Andrew Roden Contributi­ng Writer rail@bauermedia.co.uk

A LACK of lookouts was partially responsibl­e for the deaths of two track workers at Margam East Junction in south Wales on

July 3, according to an interim report published by the Rail Accident Investigat­ion Branch on December 5.

The two men were working on points P9577B when they were struck by a Swansea-London Paddington train, operated by Great Western Railway, at around 0952 ( RAIL 883).

The report says that three workers at the site (one of them survived) were almost certainly wearing ear defenders because a loud power tool was being used, and that none was aware a train was approachin­g until it was too late to move to a position of safety.

“The absence of a lookout with no involvemen­t in the work activity removed a vital safety barrier,” says the report.

Paperwork issued to the team was also scrutinise­d. RAIB found that one safe work pack (SWP) identified two safe systems of work. The first was that work on the Up Main line at Margam

East Junction was to take place between 1230 and 1530 and that a line blockage had been arranged. The second system (designated ‘parallel’) indicated that work could take place on both Main lines with warning provided by lookouts between 1230 and 1530.

However, another SWP was created on June 27 for work on

July 3, relating to another worksite near crossover 9550 - 1.6 miles from Margam East Junction in the direction of Cardiff. One of the two safe systems of work stated that work on the Down Main line would take place between 0830 and 0930 protected by blockages between 0830 and 0930. The other (also designated ‘parallel’) indicated that work could take place on both main lines with warning provided by lookout at those times.

RAIB says the presence of two separate SWPs, one for work near crossover 9550 and the other for work at Margam East Junction in the afternoon, “appears to suggest an intention that work at the two locations be carried out sequential­ly”.

However, it adds that witness evidence suggests some of those involved did not interpret the paperwork in that way.

“There appears to have been a widespread belief that the times shown on the SWPs related only to the availabili­ty of line blockages, rather than determinin­g when the work at each location could take place. RAIB observes that 12 workers would have been far more resource than was needed to carry out each of the work activities that had been identified at each site,” the report says.

It adds that the two systems of work recorded in the SWP for Margam East Junction were interprete­d to mean that work could be carried out on either the Up or Down Main line with only unassisted lookout warning, with the option of taking line blockages from 1230 if needed.

In its report, RAIB says: “The RAIB observes that the plan for the work at Margam East Junction provided no clarity on the safe system of work that should be adopted for each element of work. It provided two parallel safe systems of work

- a line blockage on the Up Main line with a parallel safe system of work, based on unassisted lookout warning, on the Down Main line.

“However, the document could also be reasonably interprete­d as also allowing work on the Up Main line using unassisted lookout warning. This lack of clarity and understand­ing may have allowed the planner, supervisor­s and workers to believe that they had freedom to choose the system of work the group should adopt, rather than working to the plan and the times of the planned blockages.”

The report identifies that there was insufficie­nt visibility of approachin­g trains in the area for a single site lookout to provide adequate warning time for the work at points 9577B, but that the system of work in the SWP did not specify the need for a distant lookout.

RAIB also concludes that the system of work the Controller of Site Safety proposed to implement before the work began was not adopted, and that alternativ­e arrangemen­ts “became progressiv­ely less safe as the work proceeded that morning”.

Further investigat­ion will review the group of track workers’ dynamics, an assessment of working practices at Port Talbot depot at the time of the accident (with a particular focus on the way maintenanc­e teams were managed and supervised), and an examinatio­n of the arrangemen­ts in place to monitor compliance with track safety rules.

It will also review the selection, training and assessment of the track workers, particular­ly those with responsibi­lity for leading groups, and examine the organisati­onal culture and its impact on safety behaviours.

RAIB will continue to examine the suitabilit­y of the planned system of work, and review NR policies relating to: enabling sufficient track access for maintenanc­e activities; the extent of management knowledge of the informal and non-compliant systems of work that appear to have become establishe­d; and how widespread these were at Port Talbot and elsewhere.

The actions of the industry to reduce the occurrence of accidents and near misses involving track workers in the years leading up to the accident will be examined.

And the effectiven­ess of the warnings provided by the train’s warning horn in all of its possible settings will be evaluated.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from United Kingdom