Rail (UK)

Say it quietly… electrific­ation is back on the agenda

- David Clarke Technical Director, Railway Industry Associatio­n rail@bauermedia.co.uk

THIS July marks three years since the Government announced the cutting back of electrific­ation schemes across the UK.

The Great Western Main Line from Cardiff to Swansea, the Midland Main Line from Kettering to Sheffield, and the Windermere Line were all victims of a curtailed electrific­ation programme in the wake of rising costs on Great Western.

As then-Secretary of State for Transport Chris Grayling said in his Written Ministeria­l Statement at the time, the focus would now be on improving journey times with “state-of-theart trains, instead of carrying out disruptive electrific­ation works along the whole of these routes”.

Three years later, the Department for Transport published its Decarbonis­ing

Transport: Setting the Challenge Green Paper as the industry began the first week of lockdown due to the Coronaviru­s outbreak.

The document heralded a significan­t change in policy, a shift in the Government’s view of electrific­ation. Contained within it, the policy said that the Government “recognise that electrifyi­ng more of the railway is likely to be necessary to deliver decarbonis­ation”.

On rail freight, the document said that “direct government interventi­on to roll out further electrific­ation” will be required.

The shift in policy is clear. And when taken with the imminent Network Rail-led Traction Decarbonis­ation Network Study (TDNS, which is set to recommend a significan­t amount of electrific­ation work) and NR Chief Executive Andrew Haines’ comments on the need for electrific­ation ( RAIL 905), it is obvious the wind is changing.

The key question the industry needs to ask ourselves now is: how did we get here and, more importantl­y, what comes next?

The decarbonis­ation challenge

In the past, business cases for electrific­ation projects were made on the journey time improvemen­ts and the lower long-term costs for an intensivel­y used route. But increasing public awareness of the UK’s impact on climate change has meant a rightful shift of focus to electrific­ation’s green credential­s.

For transport, the need to decarbonis­e is becoming a bigger concern as other industries reduce their emissions.

As the Committee on Climate Change reported, transport continues to be the largestemi­tting sector in the UK, accounting for 27% of greenhouse gas emissions in 2016. And worryingly, transport is the only sector where emissions are still growing.

Of course, cars, vans and HGVs make up the most significan­t source of emissions. But while rail accounts for less than 1% of total transport emissions, there is a consensus in the industry that rail could be left behind if we become complacent.

The growing pressure on the Government to act on climate change was the likely reason for then-Rail Minister Jo Johnson’s announceme­nt in 2018 that the rail network would remove all diesel-only trains from the network by 2040. The industry was set the challenge of assessing how this could be done, with an industry taskforce formed - led by Angel Trains Chief Executive Malcolm Brown.

Lower electrific­ation costs

Meanwhile, the Government was under growing pressure to review electrific­ation’s role in the future of the rail network. The Transport Select Committee had launched an inquiry into rail infrastruc­ture investment, and its findings in the summer of 2018 were clear: “Electrific­ation should be delivered through a long-term rolling programme in which the Department, Network Rail and the wider industry learn the lessons of earlier schemes and strive to reduce the costs.”

However, as the TSC highlighte­d, the ultimate barrier was cost, with cost overruns on the Great Western Electrific­ation Programme (GWEP) in particular having had a damaging effect on the Government’s confidence in the industry to deliver. Throughout 2018 it was increasing­ly clear that if the Government was to sign off future schemes, that confidence needed to be restored.

That was the aim when the Railway Industry Associatio­n (RIA) began putting together its

Electrific­ation Cost Challenge. The report, published in March 2019, sought to review past projects such as GWEP and assess how cost-effective electrific­ation can be delivered.

Contrary to public perception, the report found that many electrific­ation schemes in the UK were being delivered to time and budget. While the problemati­c schemes are often the most well-publicised, 75% of the schemes analysed across the UK and internatio­nally

were being delivered at the right cost.

The report showed that around £0.75 million to £1m per standard track kilometre (STK) for simple projects and around £1m to £1.5m/STK for more complex ones should be the benchmark for appropriat­e overhead line cost. And there are examples of recent schemes that have been delivered at that rate - including most Scottish projects, the Midland Main Line and the Bristol-Cardiff section of Great Western.

The report also had a lot to say about GWEP, where novel technologi­es had not been sufficient­ly tested before use and where insufficie­nt planning and premature cost estimates had led to an increase in cost.

In particular, a ‘high output’ system was developed for GWEP to maximise productivi­ty of delivering overhead line electrific­ation through a ‘factory train’. However, this overlapped with design and delivery of the

“Increasing public awareness of the UK’s impact on climate change has meant a rightful shift of focus to electrific­ation’s green credential­s.”

scheme, leading to poor productivi­ty that could not be recovered due to a completion date which had been set before the scheme was fully planned.

The report identified the lessons and good practice from the Great Western programme and other contempora­neous projects and demonstrat­ed that if these are applied electrific­ation can be delivered efficientl­y.

The Rail Industry Decarbonis­ation Taskforce reported back in July 2019, setting out how the industry could meet the Minister’s challenge of decarbonis­ing by 2040. Its report set electrific­ation in context, looking at what solutions would be necessary on different parts of the route. The report set out three different types of rail line:

■ Category 1: The core network, where traffic is most intense and thus there is a business case to electrify. Delivered via rolling electrific­ation programme. ■ Category 2: The parts of the network for which, due to lower traffic levels or long distances, there is unlikely to be a business case for continuous electrific­ation. On these lines there is an opportunit­y to introduce new zerocarbon technology in volume within five years, as existing fleets come due for replacemen­t (such as in hydrogen technology).

■ Category 3: The parts of the network between so-called Category 1 and 2, served in the medium term by bi-mode trains that draw power from the OLE in electrifie­d areas, but which are self-powered ‘off the wires’ currently by diesel. Here a rolling programme of electrific­ation would be needed, with new low-carbon technologi­es such as batteries used for ‘hopping’ between wired rail.

The report, alongside RIA’s Electrific­ation

Cost Challenge, provided a clear path to decarbonis­ing the network.

Changing political consensus

A new Prime Minister in July 2019 led to a Government reshuffle and a change to the Ministeria­l team at the Department for Transport.

When the General Election was then called in December 2019, it was a welcome surprise to see all main national political parties commit in their manifestos to the continued electrific­ation of all transport modes, marking a considerab­le shift in view (particular­ly from the Conservati­ves).

However, the shift in policy should perhaps not be a surprise, with the Government’s ‘levelling up’ agenda focusing on regional growth and with a strong impetus for green growth - both make further electrific­ation work particular­ly attractive.

Of course, the Coronaviru­s pandemic will have an impact on our rail network, but for a Government seeking an environmen­tal economic bounce-back, electrific­ation remains a worthwhile investment.

What comes next?

The industry is clear that any future electrific­ation work needs to be delivered in a rolling programme where investment is predictabl­e and smoothed over the medium to long term, so that the industry can build up capabiliti­es to deliver cost-effectivel­y.

Last year, Network Rail began work on its

Traction Decarbonis­ation Network Study (TDNS), with an interim report to be published in July and the full report in October. It is expected that this will recommend a rolling programme of work that will result in the frontier of electrific­ation being extended across the UK, without repeating the ‘ boom and bust’ approaches to electrific­ation that the UK has experience­d in the past.

Simultaneo­usly, there is also pressure from political leaders in the Midlands and Wales to reinstate plans that were cut back in 2017, as well as to fully electrify projects like the transPenni­ne route and East West Rail.

The sooner the Government moves on, the better. Work concluded in January on BristolCar­diff and work to electrify the Midland Main Line is almost complete. Without further work, the current expertise that the sector has built up will dissipate as skilled workers move to other sectors.

On the other hand, an early decision creates the opportunit­y to both retain these jobs and create many more, as the industry ramps up to the decarbonis­ation challenge ahead.

There is a ‘burning platform’ to get the rolling programme establishe­d, particular­ly given the time required to plan for work. There is always the threat of ‘paralysis by analysis’, where reviewing plans leads to projects getting postponed indefinite­ly.

Conclusion

The prospects are good for electrific­ation, and there has been a considerab­le shift in Government and client attitude to projects. Industry also recognises that it has a responsibi­lity to continue to deliver efficientl­y.

Now we need to proceed at pace with getting new schemes to market, so that we can achieve the Government’s aims of decarbonis­ing our rail network by 2040.

 ?? COLIN POTTLE. ?? GB Railfreigh­t 66779 passes beneath newly erected overhead line equipment on the Midland Main Line near Wellingbor­ough, with a service to Ketton cement works on May 19. Three years after scrapping plans to erect wires on the MML all the way to Sheffield, Derby and Nottingham, Government has indicated that it could begin to sanction new electrific­ation projects once again.
COLIN POTTLE. GB Railfreigh­t 66779 passes beneath newly erected overhead line equipment on the Midland Main Line near Wellingbor­ough, with a service to Ketton cement works on May 19. Three years after scrapping plans to erect wires on the MML all the way to Sheffield, Derby and Nottingham, Government has indicated that it could begin to sanction new electrific­ation projects once again.
 ??  ??
 ??  ??

Newspapers in English

Newspapers from United Kingdom