Rail (UK)

Network Rail delivers an efficient start to Control Period 6

-

THE Office of Rail and Road (ORR) has an important responsibi­lity to hold Network Rail to account in the interest of passengers, freight customers, funders and taxpayers.

Network Rail has been provided with £35 billion to operate, maintain and renew Britain’s railways in Control Period 6 (CP6, April 2019March 2024). It’s our job to provide assurance that it does this efficientl­y, effectivel­y and safely.

CP6 is vastly different to CP5 (April 2014March 19), and necessaril­y so. Things went wrong early in CP5, with shortcomin­gs in Network Rail’s planning which led to delays in delivery, cost overruns and a cycle of constant re-planning, all of which undermined the company’s efficiency. This could not go on, so for CP6 both ORR and Network Rail have made significan­t operationa­l changes.

Core to this has been the role of devolution within Network Rail. In contrast to CP5, the company’s plans for CP6 were developed by its devolved teams (rather than the centre), with much greater local ownership than before. Network Rail has since consolidat­ed this, with its shift to a regional structure and the appointmen­t of Regional Managing Directors. In ORR we have mirrored this with dedicated regional leads and region-based settlement­s.

We have also changed our oversight and assurance of the company, with a greater focus on leading indicators which makes it easier to intervene at an earlier stage, to prevent issues escalating. And when we do intervene, we can target specific regions. Additional­ly, we have new sanctions available, including hearings and the ability to apply financial penalties to management bonuses (for example, at regional level), rather than issuing fines that reduce Network Rail’s overall funding.

Beyond our safety role, our main focus on Network Rail is making sure that the company gets it right on efficiency, train performanc­e, and delivering the work it promised to do to look after its assets sustainabl­y.

First regional annual assessment

Year one of CP6 has been the first test of the new approach. Our recently published annual assessment shows that overall there has been a good start, with Network Rail achieving significan­t efficienci­es following ORR’s early interventi­on, and delivering its planned works to improve network condition.

It is the first time we have been able to compare regions in our assessment, which has been useful. We have identified variations in train performanc­e across regions, showing best practice and where improvemen­t is needed. It has allowed us to take targeted action during the year - for example, on Network Rail’s contributi­on to poor performanc­e in the North West & Central region.

On track for improved efficiency

The most pleasing aspect in year one is that for the first time in many years, Network Rail has not only delivered its efficiency targets, but exceeded them. It delivered better than planned efficiency savings on its operations, support, maintenanc­e and renewals activities - £385 million of efficiency, ahead of its £316m commitment.

This comes off the back of a lot of hard work by both ORR and Network Rail. On our part, we have been relentless in seeking clarity on how Network Rail was going to deliver on its efficiency promises (again, learning from CP5) - and it has responded well. But we don’t want to get ahead of ourselves. There will be impacts from COVID-19, and there are more challengin­g efficiency targets ahead.

Network Rail must continue to plan effectivel­y to meet these challenges, and we have been monitoring its preparatio­ns. For example, the percentage of bookings for engineerin­g works in 2020-21 (76%) is behind the company’s internal target and lower than last year. This represents a risk to efficient delivery in 2020-21. We are staying on the case and Network Rail is responding positively to our challenge.

A focus on performanc­e

Passengers largely judge the railway based on whether their trains are reliable and punctual. And while it is now a completely different world in terms of passengers’ use of the railway, after COVID-19, it is still important to look at what happened in 2019-20 and at Network Rail’s contributi­on.

Our annual report highlights the variations in performanc­e across the network. Where delays are higher, it pinpoints the causes.

Using the measure of Network Rail-caused delay, we can see that performanc­e in Wales & Western was best. In particular, the region successful­ly implemente­d a large timetable

change while maintainin­g performanc­e, and is now sharing that best practice with other regions. Performanc­e was also good in Southern.

Performanc­e was lower than target in North West & Central, Network Rail Scotland, and Eastern regions. In North West & Central, it fell below the minimum level that we set for both freight and passenger performanc­e, and as a result we investigat­ed. We found that the region was taking performanc­e improvemen­ts very seriously but had not, at the time, produced time-bound improvemen­t plans. It has now produced these and must deliver them. We will monitor progress and take action if delivery stalls.

Rightly, NR’s focus is now on its response to the Coronaviru­s pandemic, but it must continue to address underlying performanc­e issues across the network. Analysis of the relationsh­ip between service levels and performanc­e during the past four months will provide further insights, and we’re pleased with how the company is working with operators on this.

Improved infrastruc­ture reliabilit­y

Going hand in hand with performanc­e is the reliabilit­y of the infrastruc­ture- if you cut the number of asset failures, then there are fewer delays. And what we’ve seen is that while Network Rail is delivering its plan to renew the railway, the reliabilit­y of some assets has worsened in the past year. For example, there was an increase in overhead line issues in the Eastern region.

To minimise the impact of asset failures it is vital that Network Rail continues to improve the resilience of the network, including against severe weather. It must also continue to carry out essential inspection and maintenanc­e work to identify and rectify defects and failures in a timely way - and improve its reporting in this area. We will review how it is progressin­g on this important work.

Rising to the challenge of COVID-19

As part of our annual assessment, we looked at Network Rail’s initial response to COVID-19. And we’ve seen that its response - and the whole industry’s response - has been quick, decisive and impressive.

At ORR we asked the industry: “What do you need from us?” We responded promptly to multiple requests for new guidance and took a pragmatic approach to our data requiremen­ts to help reduce the burden, so that the rail industry could focus on transporti­ng essential workers and goods. But we made it clear that Network Rail still had obligation­s and still needed to be held to account.

There is also a lot of unfinished business from 2019-20 - for example, on how Network Rail uses scorecards to provide transparen­cy to its customers and funders.

And there will be new challenges and opportunit­ies for Network Rail this year. The Government wants to see how infrastruc­ture spend, particular­ly on enhancemen­t projects, can be increased to support the economy and how projects can be delivered faster. We are working with NR on how we can use our experience in authorisin­g projects to highlight where improvemen­ts could be made.

What’s next?

While year one of the Control Period has only recently ended, there are good signs that the devolved structures of ORR and Network Rail, and our focus on greater early interventi­on, are bringing benefits.

There’s more to do, and we will continue to focus in particular on efficiency, performanc­e and overseeing NR’s delivery of its promised commitment­s. While the future shape of rail travel is unclear, we want to make sure that Network Rail is well placed to play its part.

“We have been relentless in seeking clarity on how Network Rail was going to deliver on its efficiency promises, and it has responded well. But we don’t want to get ahead of ourselves. There will be impacts from COVID-19 and there are more challengin­g efficiency targets ahead.”

 ??  ??
 ??  ??
 ?? KEITH DUNGATE. ?? Northern 331109 emerges from Springs Tunnel (near Guiseley) on June 25, forming the 1440 Ilkley-Leeds. This section of line is located within Network Rail’s Eastern Region, where performanc­e was lower than target in 2019-20.
KEITH DUNGATE. Northern 331109 emerges from Springs Tunnel (near Guiseley) on June 25, forming the 1440 Ilkley-Leeds. This section of line is located within Network Rail’s Eastern Region, where performanc­e was lower than target in 2019-20.

Newspapers in English

Newspapers from United Kingdom