Rail (UK)

Electrific­ation

The story behind BR’s landmark decision to adopt 25kV AC 50 cycles as the standard for overhead line eletrifica­tion.

-

Railway electrific­ation in Britain has a diverse history. Its first use dates from the late 19th century and there were a number of applicatio­ns during the first two decades of the 20th century.

Opened in 1893, the Liverpool Overhead Railway (the so-called dockers’ umbrella) used electric traction from the start, while the Mersey Railway between Liverpool and Birkenhead converted from steam to electric in 1903.

Prior to railway grouping in 1923, several companies tried third or fourth rail direct current (DC) schemes, while there were several experiment­s with both alternatin­g current (AC) and DC overhead line systems.

Indeed, at the time there was no national power grid or standardis­ation among electricit­y producers of voltage or frequency. This restricted electrific­ation schemes to what a single power station could deliver in an economic radius at a voltage and frequency suitable for conversion for use in variable speed traction motors on a train.

After the Grouping, the Southern Railway adopted third rail DC traction power supply at 660-750V DC.

In 1926, 50 cycles (hertz) frequency became the national standard for electricit­y production. Following this, the Government’s Weir Committee chose 1,500V DC via an overhead line for new railway electrific­ation projects, because it was better suited to heavier train haulage than that used on the Southern Railway.

After nationalis­ation and the creation of the British Transport Commission (BTC), with British Railways as its largest constituen­t, the BTC set up the Railway Electrific­ation Committee. The Committee met in 1951 and reaffirmed the Weir Committee standard of 1,500V DC.

Prior to the Second World War, the London & North Eastern Railway had authorised electrific­ation of its routes between Manchester-Sheffield Victoria/ Wath and Liverpool Street-Shenfield. Both schemes were completed post-nationalis­ation in 1954 and 1949 respective­ly, using the national standard.

The Railway Electrific­ation Committee did, however, propose the trial of a 50 hertz system, and the former Midland Railway lines between Lancaster, Morecambe and Heysham were chosen. These had been electrifie­d by the Midland Railway in 1908 at 6,600V AC 25 hertz, using a supply from the MR’s power station at Heysham, and so the overhead line equipment was therefore already in place.

The first three-car electric multiple unit started running in August 1953. And while there were some problems with interferen­ce to telecommun­ications, overall the experiment was judged to be a success.

With optimism for the future, BR’s 1953 annual report commented that the BTC’s capital asset needs had been clearly assessed and that several important lines of developmen­t were in hand.

Electrific­ation schemes at various stages of considerat­ion included Liverpool Street to Enfield and Chingford, King’s Cross outer suburban, and reactivati­on of the Southern Railway’s 1946 plans for all routes east of a line drawn between Reading and Portsmouth. Since the 1953 report was written during 1954, the notes of optimism for the future are interestin­g.

The Modernisat­ion Plan prepared during 1954 and announced in 1955 included £120 million for main line electrific­ation and £ 65m for new and already authorised but not yet announced suburban schemes. The May 1955 announceme­nt of electrific­ation projects included the lines in Essex and the West Coast route from Euston to the West Midlands and the North West by the overhead system, and Kent by the third rail.

At the time, there was disappoint­ment in some quarters at the apparent slow progress with these projects. Part of the reason was that the BTC’s Technical Committee was wrestling with whether to continue with 1,500V DC or whether to emulate developmen­ts in France, where the Valencienn­es to Thionville route had been wired at 25kV AC.

The Technical Committee first considered the topic on March 11 1954, when SNCF progress was discussed, and it was decided to carry out a technical and engineerin­g appraisal for a typical main line.

On May 13, both the Eastern and London Midland Regions were selected for a cost comparison between 25kV and 1,500V DC, and it was felt that more experiment­al rolling stock was required.

The implicatio­ns of 50 hertz power supply were set out in a report to the Technical Committee in September 1954, and this was followed up in January 1955 in a memo saying that investigat­ions were to continue into several technical issues. French Railways was consulted because of the significan­t progress it had made in this field.

The BTC’s Chief Electrical Engineer S B Warder continued evaluating options, and he reported to the Technical Committee on September 29 1955. His report took account of practice on the continent, where DC overhead line electrific­ation was much more extensive and where there was no logic to changing existing equipment until it became life-expired. Countries that had commenced new schemes had opted for 50 hertz, even if they already had routes which had been electrifie­d at 1,500V DC.

Warder argued that technology and the cost of equipment had moved on from the factors that influenced the Railway Electrific­ation Committee to continue with 1,500V DC, not least because it was now much less attractive economical­ly.

For example, 50 hertz offered a 32% saving in copper and 83% in steel for overhead line structures, because the overhead line could be half as large and this reduced the size of the supports. Warder estimated that an AC locomotive would cost 10% less than its DC equivalent.

Voltage drop between the source and final applicatio­n of power meant the lower-voltage DC approach needed substation­s at more frequent intervals, and therefore more highvoltag­e cables to the substation­s. On the

Manchester- Sheffield/ Wath system, the interval between substation­s was every 6.2 miles compared with an estimated 250 miles for 25kV supply.

High-voltage AC power could now be delivered direct to the traction unit, reducing the number of substation­s. This meant that one set of cables could send power to the train, instead of those from the national grid to the substation and another set (the catenary) from there to the train.

When it came to traction, however, technology had not advanced sufficient­ly for the use of AC traction motors. In any event, DC motors had evolved to the point where they were relatively lightweigh­t and very rugged, with a traction characteri­stic wellsuited to rail applicatio­ns.

The 25kV supplied to the traction unit had to be reduced to around 1,000-1,800V for the traction motors, and this was done by a transforme­r. The driver selected the power he needed from the transforme­r, and this was then rectified from AC to DC for the traction motors. This meant that each motor received an independen­t supply from the transforme­r (that is, the motors were connected in parallel).

Where 1,500V DC was drawn from the catenary, it passed through resistance­s in order to control the supply to the motors, and so energy was lost in the form of heat in the resistance­s. Only when all the resistance­s had been cut out was the highest economy in running achieved. Additional­ly, driver control was judged by footplate crew to be easier for AC traction.

Moreover, with DC supply transmissi­on to the motors was sequential (that is, from motor to motor) or in series, and this offered an inferior traction characteri­stic to connection in parallel.

Demonstrat­ing the difference in traction characteri­stic between the two systems, in France, using AC power supply and DC traction motors, a 78-ton locomotive had restarted a 2,400-ton train on a 1-in-100 gradient, while two other locomotive­s had achieved a world record speed of 200mph. For routine service, French Railways permitted a 970-ton load limit to its DC line supply electrics and 1,400 tons to equivalent AC ones.

Counterbal­ancing these factors, the much higher voltage required significan­tly larger clearances under overhead structures ( bridges, tunnels and station canopies), and rebuilding these therefore added to the cost.

To minimise this, Warder put forward the option of a dual-voltage arrangemen­t whereby 25kV would be used generally, but with 6.25kV (a quarter of 25kV) used in (for example) the London inner suburbs in order to avoid rebuilding structures. Some of the new Eastern Region schemes had this dual-voltage approach, but research subsequent­ly permitted a smaller clearance and the lower voltage was abandoned.

On the West Coast route from Euston, freight train load limits for a single locomotive were estimated to be 900 tons for DC but 1,250 tons for AC. A maximum axle-load of 20 tons and maximum tractive effort of 60,000 pounds were laid down, and the power output needed for express passenger work was predicted to be around 3,500hp.

It was estimated that for services between Euston, Birmingham, Liverpool and Manchester, a total of 150 passenger and 510 mixed-traffic AC electrics would be needed at a total cost of £ 38.3m. For a DC system the number of mixed-traffic machines was given as 570, but each locomotive cost less and so the overall figure was £ 36.4m. A larger number of DC machines were needed to handle the maximum anticipate­d trailing loads.

In advance of Warder’s report, cost estimates for the proposed West Coast scheme out of Euston were produced, based on both AC and DC overhead supply. The figure of £118m represente­d a saving of £ 6m for the former.

Interferen­ce with telecommun­ications and colour-light signalling was also an issue that,

unexpected­ly, was found in some places to require complete replacemen­t of existing colour-light equipment. In conclusion, Warder favoured AC supply because of its superiorit­y in the areas of power supply, fixed equipment and rolling stock.

The Technical Committee accepted Warder’s report and, together with that containing cost estimates for the West Coast, it was reviewed by the BTC on October 19 1955. The BTC deferred its agreement until the 27th, when the chairmen of the Area Boards and their Regional Managers were consulted. Future Southern Region schemes would, however, continue with the third rail system.

The Technical Committee was asked to investigat­e the implicatio­ns for converting the Eastern Region’s London suburban schemes that had already been authorised at 1,500V DC to 50 hertz. It reported that the lines from Shenfield to Chelmsford and Southend would be electrifie­d as authorised, but converted to the new standard later.

The national standard for main line electrific­ation was a government-directed matter, and accordingl­y the Commission informed the Ministry of Transport (MoT) of its intention to change to 25kV as the new standard.

A note dated December 3 1955 in the MoT files observes that the creation of the BTC had removed the need for government to opine on this matter. On May 31 1956, the Commission recorded the Minister’s affirmatio­n of the decision.

The West Coast route from London to the North West was chosen to be the first main line for 50 hertz electrific­ation. At the time, the Eastern Region was fully committed with London suburban schemes and lacked the resources to handle the East Coast route as well, which was deferred in consequenc­e.

The BTC also discussed the West Coast scheme on October 27. H P Barker was an industrial­ist and part-time Commission member, and he proposed that the whole scheme be approved, but the profession­al railwaymen wanted to deal at first only with the Crewe-Manchester section to prove the 50 hertz concept.

Barker said the system had already been proved overseas and that only the equipment needed to be trialled, but he was overruled. He was, of course, right - and this decision not to sanction and start the whole project nearly caused it not to go ahead. This was because the Minister of Transport and Prime Minister in 1960 were unconvince­d about its viability when compared to diesel traction. The go-ahead did come eventually, but at the price of higher costs and delays.

Barker’s proposal to try out new equipment before mass introducti­on should also have been heeded, because traction components bought without trialling for the Glasgow and Great Eastern schemes gave trouble.

His proposal in 1954 for a trainset that could be serviced and reversed in a terminal station for its next duty was also rejected as impractica­l by the profession­al railwayman, only for such a train to appear six years later as the ‘Blue Pullman’ ( RAIL 910).

The most powerful electrics built for the Manchester-Sheffield/ Wath scheme in 1954 weighed 104 tons, were rated at 2,500hp, and were permitted 90mph.

By contrast, the prototype 50 hertz locomotive­s delivered in 1960 for the West Coast weighed no more than 80 tons, had a continuous rating of 3,000-3,300hp and a top speed of 100mph.

Such was the progress in technology and design philosophy over just six years. Sixtyfive years on, Warder’s decision to opt for 50 hertz has been vindicated.

 ?? AEI. ?? The prototype 1,500V DC locomotive built by the London & North Eastern Railway in 1941, undergoing trials on the Manchester South Junction & Altrincham route.
AEI. The prototype 1,500V DC locomotive built by the London & North Eastern Railway in 1941, undergoing trials on the Manchester South Junction & Altrincham route.
 ?? AEI. ?? The large bulk of 1954-built DC 77004 is evident in this view at Manchester Piccadilly of a Sheffieldb­ound train. Note also the substantia­l overhead line supports.
AEI. The large bulk of 1954-built DC 77004 is evident in this view at Manchester Piccadilly of a Sheffieldb­ound train. Note also the substantia­l overhead line supports.
 ?? RAIL PHOTOPRINT­S/REG BARON. ?? The Lancaster-Morecambe electrific­ation was converted from 25 to 50 hertz in 1953 for assessment. In 1965, M28222 departs Lancaster Green Ayre with a service for Lancaster Castle.
RAIL PHOTOPRINT­S/REG BARON. The Lancaster-Morecambe electrific­ation was converted from 25 to 50 hertz in 1953 for assessment. In 1965, M28222 departs Lancaster Green Ayre with a service for Lancaster Castle.
 ?? DAVID CLOUGH. ?? Contrast the almost-diminutive AC electric 85009 with the DC machines built for the Woodhead route, as well as the much lighter electrific­ation structures at Balshaw Lane Junction (north of Wigan) on August 9 1984.
DAVID CLOUGH. Contrast the almost-diminutive AC electric 85009 with the DC machines built for the Woodhead route, as well as the much lighter electrific­ation structures at Balshaw Lane Junction (north of Wigan) on August 9 1984.
 ?? DAVID CLOUGH. ?? On a misty Boxing Day in 1969, a Class 76 approaches Guide Bridge with a Manchester Piccadilly-Sheffield Victoria train, 11 days before these services were withdrawn.
DAVID CLOUGH. On a misty Boxing Day in 1969, a Class 76 approaches Guide Bridge with a Manchester Piccadilly-Sheffield Victoria train, 11 days before these services were withdrawn.
 ?? DAVID CLOUGH. ?? West Coast electrific­ation from Euston continued to use substantia­l support masts on four-track sections. Class 86 E3120 approaches Linslade tunnel (Leighton Buzzard) with a Euston-bound service in 1972.
DAVID CLOUGH. West Coast electrific­ation from Euston continued to use substantia­l support masts on four-track sections. Class 86 E3120 approaches Linslade tunnel (Leighton Buzzard) with a Euston-bound service in 1972.
 ?? JO CLOUGH. ?? Despite spanning six tracks, the support masts on the second phase of West Coast electrific­ation are much lighter than those south of Crewe. On September 2 2019, a Class 390 forming the 1054 Blackpool North-Euston passes Wigan Springs Branch.
JO CLOUGH. Despite spanning six tracks, the support masts on the second phase of West Coast electrific­ation are much lighter than those south of Crewe. On September 2 2019, a Class 390 forming the 1054 Blackpool North-Euston passes Wigan Springs Branch.

Newspapers in English

Newspapers from United Kingdom