Rail (UK)

Philip Haigh

PHILIP HAIGH examines the arguments for and against electrific­ation, and notes a key benefit in the fight to reduce carbon emissions

- Philip Haigh Transport writer

Electric rail freight.

NOEL Dolphin is an enthusiast for electrific­ation. That shouldn’t surprise anyone because he works for Furrer+Frey, the Swiss company which developed the electrific­ation system that Network Rail installed on the Great Western Main Line.

In January, he penned a short letter to NR asking for details of a board report about the benefits of Great Western electrific­ation. Despite using the Freedom of Informatio­n Act, NR refused to release the board report, but it did send a 126-page report dated July 2020 that laid out the benefits and challenges the company encountere­d when wiring the main line west towards Cardiff and Bristol.

In the report, NR is very candid - not only in explaining the problems it had, but also in making the case for further wiring. It’s also written by someone who clearly knows their history.

It notes that before diesels appeared, electrific­ation was the only way to provide performanc­e beyond the capability of steam locomotive­s. This drove John Aspinall to electrify the Lancashire and Yorkshire Railway’s line between Liverpool and Southport ( RAIL 874), and prompted the North Eastern Railway to electrify lines in Tyneside and the London, Brighton and South Coast Railway to erect overhead wires in 1909.

The sense of history apparent in NR’s GW report comes from a footnote that explains: “In 1902 the Great Eastern Railway developed an alternativ­e narrative, supported by an impractica­lly heavy steam locomotive, to oppose plans for a rival electric railway.” That’s the sort of detail I’ve rarely seen in a NR report.

A second footnote provides a decent explanatio­n of why electrific­ation took root: “Electrific­ation has progressed since the end of the 19th century because it provided a better economic approach to railway operations, and improved performanc­e. There was not, at that time, any carbon reduction requiremen­t - economic factors drove electrific­ation widely across Europe.

“This fundamenta­l principle remains today, now overlaid with the additional benefits to the environmen­t. Electrific­ation provides for lower maintenanc­e rolling stock, and hence further lower operationa­l costs.”

The Class 165 and Class 166 diesel units that carried Great Western Railway suburban passengers to and from London Paddington managed reliabilit­y figures of 4,000-6,000 miles per technical casualty (MTIN). The electric Class 387s that replaced them are touching 20,000MTIN.

GWR’s Class 800 units reach 125mph in five miles in electric mode, compared with the 15 miles it took for a diesel HST to reach the same speed. This improved performanc­e helps deliver quicker journeys, which formed a major part of the business case for the project.

NR’s report claims a 44% operating saving from an ‘800’ running on electric compared with diesel mode, while a ‘387’ produces a 28% saving when compared with a ‘165’ or ‘166’. Which is impressive, but surely dwarfed by the £5.58 billion cost of erecting masts and wires (as anticipate­d in August 2016 and up from £2.72bn in October 2013).

Then there’s another footnotes that reveals: “The direct maintenanc­e cost for Wales and Western Region electrific­ation systems is approximat­ely £11 million. An estimated £7.5m of this relates to maintenanc­e of new assets installed by GWEP.”

This remains the challenge for electrific­ation’s advocates. It’s easy and true to say that electric trains are cheaper to buy and cheaper to operate than diesels. They also bring performanc­e benefits that can translate into faster journeys for passengers. But these savings must be offset against higher maintenanc­e costs for NR and the capital costs of erecting masts and wires that fall largely on taxpayers.

When Viscount Weir examined the case for main line electrific­ation in 1931, he found that the tipping point between steam and electric came on lines carrying more than 2.3 million trailing ton-miles per single track mile per year.

Back then the big-ticket savings came in footplate wages (which were halved as single manning of electric trains replaced the driver and fireman team on a steam footplate) and in traction repairs costs (which more than halved).

Today, we single-man all trains so that saving has evaporated, while the lower maintenanc­e costs remain an advantage.

What’s absent from electrific­ation debates now is today’s equivalent of Weir’s 2.3 million figure and an assessment of how NR’s lines measure against that figure. Without both it’s difficult to assess the case for wiring routes. Last summer’s decarbonis­ation plan from Network Rail provided no details of this kind and gave no overall sense of which lines should be prioritise­d.

I hope that changes when the Department for Transport reveals its plan to decarbonis­e England’s railway (Transport Scotland and Transport for Wales should do the same for their networks). To do this, the DfT will need to have learned lessons from its Great Western project.

As NR’s report notes, it was not until March 2015 that it created the first business case to justify decisions it had already taken to electrify the Great Western and procure new IET (Class 800) trains. Once again, it’s a footnote that hides a stiletto: “It has not been possible to locate a copy of the detailed business case document.”

Of course, business cases need decent financial figures and NR admits that its estimates were poor. It puts this down to the 20-year gap since the last major electrific­ation project and the loss of skills and experience. That’s one factor in favour of a rolling programme, but such a programme will be expensive.

It wasn’t NR’s only failure. It failed to secure legal permission for the work before starting and chose to chase 1,800 separate consents

rather than an over-arching Developmen­t Consent Order. It started work before designs were complete - it had to in order to try and meet it deadlines. In the end, the project was delivered late anyway.

But what Network Rail delivered has so far proved to be reliable. NR designed it to be reliable so that, for example, the transforme­r at Melksham can feed 200 route kilometres in case the power supply at Didcot drops out.

The overhead wires have a new tensioning system that removes balance weights (a recommenda­tion of the investigat­ion into 2002’s derailment at Potters Bar). Each line has wires that are mechanical­ly independen­t from adjacent lines, which should reduce the damage a pantograph failure might cause. The new system coped well with summer 2019’s heatwave, according to NR’s report.

But this robust system has met criticism for its bulk. Viewed from the wrong angle, it certainly spoils the Thames Valley at Goring.

Once again, the report leaves it to footnotes to reveal some truths: “To mitigate the impact, Network Rail funded lineside tree planting costing £0.75m to help screen the steel gantries and other electrical equipment along a 20km stretch of line between the outskirts of Reading and Didcot. Network Rail also funded a further £3m of landscape enhancemen­t projects within the wider corridor of the electrific­ation works along this part of the line.”

Network Rail and its contractor­s went through the mill to gain the experience they now have. It will go to waste if England does not embark on a decent electrific­ation programme.

The costs that hang heavily on Great Western’s catenary might be shared more equitably across the network if ministers in London authorise more wires. They have at hand a proven method of decarbonis­ing transport. They have modern tools and techniques. They need invent nothing.

But they must set out a compelling case. They need to explain why or not a particular route needs wiring now or later. Without these explanatio­ns, they will be doing little to assure us as taxpayers that they’re spending our money wisely.

By all means mix in the environmen­tal advantages of electrific­ation (set against the capital carbon costs of steel and concrete), but let’s see the figures.

And let’s see the programme. Let’s see which routes have the best cases. Let’s see which provide the best benefits on an overall network basis. Let’s inject some certainty.

Because there’s a counter argument. That’s the one that says rail already has very low carbon emissions and that the huge spending needed for electrific­ation does little to shift the country’s environmen­tal needle.

On one level, this is entirely true. On another level, it’s short-sighted. I don’t think electrific­ation is about rail’s carbon emissions. It’s about providing attractive services that will tempt motorists from their cars. This modal shift could do more than rail alone to cut transport emissions.

Yet I have a nagging doubt… as Volvo becomes the latest car maker to pledge a switch to electric, I fear that the longer ministers dither with rail electrific­ation, the stronger the case becomes that decarbonis­ed transport comes from electric cars.

Which does nothing for freight. I can’t see batteries powering heavy lorries any time soon and electric lorries powered by overhead wires on motorways seem fanciful at best.

To be serious about decarbonis­ing freight, Britain needs electric rail freight. There’s no other way, so ministers should forget using bimode trains to cover inconvenie­nt gaps in wires.

Passengers may not notice the brief burst of diesel (or batteries) to get over the gap, but electric freight certainly does. It forces freight to go with diesel all the way. Freight needs continuous electrific­ation if it’s to attract loads from roads.

Hence NR Chief Executive Andrew Haines telling February’s National Rail Recovery Conference that electrific­ation was the only affordable way of decarbonis­ing rail by 2050.

“Network Rail and its contractor­s went through the mill to gain the experience they now have. It will go to waste if England does not embark on a decent electrific­ation programme.”

 ??  ??
 ??  ??
 ?? JACK BOSKETT. ?? A Great Western Railway IET passes through Shrivenham on the Great Western Main Line on May 18 2019. Further electrific­ation of main lines is essential for rail freight, which offers the best solution to cutting freight carbon emissions, says Philip Haigh.
JACK BOSKETT. A Great Western Railway IET passes through Shrivenham on the Great Western Main Line on May 18 2019. Further electrific­ation of main lines is essential for rail freight, which offers the best solution to cutting freight carbon emissions, says Philip Haigh.
 ??  ?? Philip Haigh is a former deputy editor of RAIL who is now a freelance writer specialisi­ng in railways. He is an associate member of the Institutio­n of Mechanical Engineers. You can contact him at
philiphaig­h.co.uk and follow him on twitter at @philatrail
Philip Haigh is a former deputy editor of RAIL who is now a freelance writer specialisi­ng in railways. He is an associate member of the Institutio­n of Mechanical Engineers. You can contact him at philiphaig­h.co.uk and follow him on twitter at @philatrail

Newspapers in English

Newspapers from United Kingdom