Runcorn & Widnes Weekly News

Contractor helped beat bridge deadline

-

A LEADING bridge and engineerin­g services specialist helped complete the Mersey Gateway Project ahead of time and below budget.

Mabey was contracted by Merseylink to provide temporary supports for four out of the eight landside sections, which create the approach to the bridge, the largest being the Astmoor and Bridgewate­r viaduct.

The engineerin­g firm’s role was critical in supporting the bridge loads from the pre-cast concrete beams and cast in situ cast diaphragms onto the permanent concrete piers, using its temporary propping system to transfer the weight. This included developing a unique test rig for every pier arrangemen­t to guarantee it was structural­ly safe for the heaviest applied loads.

With its team, equipment and technology based just a few miles away in Garswood, Mabey had almost every element of its propping solutions in place at its peak, including the Superprop, Mat125, Mass50, Mass25, System 160, hydraulics, instrument­ation equipment, together with other specialist equipment with 65 people working on site at its busiest time.

The company implemente­d monitoring throughout the constructi­on phase, which helped facilitate the transfer of the bridge loads from the temporary propping system onto the permanent works and ensure even distributi­on.

The process was monitored by Linear Variable Differenti­al Transforme­rs, a sophistica­ted piece of technology that monitors ● movement and load.

It allowed Mabey to de-jack the loads with full control and in a synchronis­ed manner.

Mabey UK Hire chief executive Gordon MacDonald said: “Our proactive approach to providing the right resource, labour, engineerin­g and facilities is what has enabled this project to be carried out more quickly, safely and efficientl­y.

“Working with Merseylink, we quickly identified and overcame design and test loading challenges to keep the project on track.

“As our biggest UK Hire project to date, the opening of the bridge marks an iconic and proud moment in Mabey’s history.”

Nearly 90,000 cubic metres of concrete, the equivalent of 36 Olympic-sized swimming pools, was used to build the bridge, the North Approach Viaduct, and the South Approach Viaduct.

Together they measure almost 2.5km long, and the bridge’s tallest pylon rises 125m above the river.

The bridge opened to the public after three-and-a-half-years of constructi­on.

The six lane toll bridge has been built to relieve traffic and congestion at the existing Silver Jubilee Bridge.

Until this point, more than 80,000 vehicles were using the Silver Jubilee every weekday; 10 times the number it was originally designed to accommodat­e.

The improved transport link will also enable further regenerati­on of the Halton area, with easier, quicker access for building and improvemen­t works.

Merseylink’s senior operations manager Jim Rice said: “The Mersey Gateway Project signifies a major step forward in the regenerati­on of the North West.

“Mabey’s role in this project helped us overcome a number of challenges, such as determinin­g access arrangemen­ts and the specific method we would use to install the pre-cast concrete beams and avoid over-stressing the temporary propping system.”

 ??  ?? Engineerin­g firm Mabey was brought in to complete key elements of work on the Mersey Gateway bridge
Engineerin­g firm Mabey was brought in to complete key elements of work on the Mersey Gateway bridge

Newspapers in English

Newspapers from United Kingdom