Steam Railway (UK)

THE ROSTER

LoCoMotIve­s IN foCus

- TONY DAVIES

Dunrobin: South Devon Railway Engineerin­g is constructi­ng replacemen­t driving wheelsets for the former Duke of Sutherland’s 0‑4‑4T, which is undergoing a contract overhaul at the Severn Valley Railway for use at Beamish.

1369: The overhaul of the unique ex‑Weymouth and Wadebridge ‘1366’ 0‑6‑0PT is nearing completion at the South Devon Railway, with the bottom half finished and new pannier tanks produced. Its boiler has had a new three‑quarter section welded into place on the firebox backhead, while the firebox foundation ring is being riveted into place and the stays fitted.

However, the boiler overhaul suffered a setback when a new set of tubes were delivered but found to have been stamped with a material batch number, rendering them fit only for scrap. A replacemen­t set has been obtained with some difficulty, as GWR tubes are an odd size.

Explained South Devon Railway Trust director Richard Elliott: “The depth of the stamping was such that it represente­d a fair percentage of the permitted wastage on tubes, so they were half worn‑out before we started, and could have failed or started to leak early. The issue has been taken further by higher authority.”

It had originally been hoped to finish the engine in 2018, but Mr Elliott said: “We’re now aiming for February half‑term week – we have lots of other routine stuff to deal with, as well as the rest of the running fleet!”

4150: The boiler of the ex‑Barry ‘5101’ 2‑6‑2T entered the workshops at Bridgnorth on October 30, with work commencing immediatel­y to remove its old stays and make new injector delivery pipes. The overhaul of the boiler is the biggest remaining task in the 40‑year restoratio­n of the ‘Large Prairie’, which arrived at the Severn Valley Railway (from the Dean Forest Railway) in 1978 and is the last ex‑Barry engine still to steam on the SVR. Its owning group, the 4150 Fund, is putting the finishing touches to the engine’s bottom half at Bewdley, including fitting the cylinder cladding, drain cocks, and cab controls.

4920: Although removed from its isolated siding and placed under cover at the South Devon Railway in April, Dumbleton Hall does not yet have a place in the overhaul queue at Buckfastle­igh. However, one small step has been taken towards returning it to steam – the pressing of a replacemen­t firebox backhead, in conjunctio­n with two more, for Hagley Hall (see below) and ‘28XX’ 2‑8‑0 No. 2807 (which is in traffic at the Gloucester­shire Warwickshi­re Steam Railway, but reaches the end of its current ‘ten‑year’ boiler certificat­e in 2020).

Richard Elliott, chairman of the Dumbleton Hall Preservati­on Society and a director of the South Devon Railway Trust, said: “The DHPS is obviously keen to see it run as soon as possible, but we accept that the SDR has more pressing priorities. However, the DHPS is looking at ways of raising money to move the job on in the background.”

4930: In a carefully planned logistical exercise that was dryly described as “widespread geographic­al reorganisa­tion in its overhaul”, Hagley Hall’s driving and bogie wheelsets were transporte­d back from the South Devon Railway (where their tyres have been re‑profiled) to the Severn Valley Railway on October 30. The lorry was also carrying a newly pressed firebox backplate and throatplat­e for the Collett 4‑6‑0’s boiler.

On arrival at Bridgnorth, the wheels were unloaded. Their place on the vehicle was taken by four newly cast cylinders – two for Hagley Hall and two for Dinmore Manor Locomotive Ltd’s ‘2884’ 2‑8‑0 No. 3850 – which were on their way to a West Midlands engineerin­g firm for machining.

On the final leg of the journey, the boiler platework was delivered to Northern Steam Engineerin­g at Stockton, which is overhaulin­g No. 4930’s boiler.

Donations to the project can be made by texting ‘HALL29’ and £amount to 70070. Funds are being raised by the Friends of Locomotive 4930 Hagley Hall, whose website is at www.4930hagley­hall.org.uk

5539: Hugh Shipton’s GWR ‘4575’ 2‑6‑2T should have a complete ‘rolling chassis’ by the end of 2019, says John Buxton, managing director of the Barry Tourist Railway.

The ‘Small Prairie’, formerly one of the ‘Barry Ten’ collection and previously based at Llangollen, is being restored in the BTR’s ‘Barry New Works’ – which is working on the locomotive five days a week.

Since its frames were placed back on the driving wheels last June (SR469), No. 5539’s pony trucks have been refitted, along with most of the brake gear, and the valve gear will follow to complete the bottom half; the boiler remains at Llangollen for overhaul. Said Mr Buxton: “We’ve got all the bits for it,

with the help of the Llangollen and Dean Forest railways.”

6686: The wheelsets have been removed from the GWR ‘56XX’ 0‑6‑2T at the Barry Tourist Railway, and the frames are being needle‑gunned and painted. A quote for tyre turning has been obtained from South Devon Railway Engineerin­g.

6990: Great Central Railway‑ based Witherslac­k Hall is visiting the Severn Valley Railway to bolster the steam fleet for the Santa Specials. The ‘Modified Hall’ was due to arrive in late November and stay until early January.

7828: Odney Manor is expected to return to traffic on the West Somerset Railway in December, in the guise of ‘Norton Manor, 40 Commando’, reprising the identity it carried in 2011 in honour of HM Royal Marines 40 Commando, who are based at the nearby Norton Manor camp.

W8: ‘Terrier’ Freshwater was steamed for the last time at the Isle of Wight Steam Railway on October 31, to test a new set of injector cones that had been manufactur­ed from solid bar in Havenstree­t workshop. It will remain on public display in ‘Train Story’ during December and still appear externally complete, says Locomotive Foreman Andrew Summers, but work will have started to strip out the boiler tubes, smokebox and cab fittings for its forthcomin­g overhaul.

825: The boiler of the Essex Locomotive Society’s ‘S15’ passed its out‑of‑frames steam test at the North Yorkshire Moors Railway’s Grosmont works on November 2.

34039: With the completion of the replacemen­t fireboxes for ‘Battle of Britain’ No. 34059 Sir Archibald Sinclair (Bluebell Railway) and ‘West Country’ No. 34101 Hartland (North Yorkshire Moors Railway) the boiler of Great Central Railway‑ based No. 34039 Boscastle has reached the head of the Bulleid boiler queue at South Devon Railway Engineerin­g. Its firebox backhead has been cut away in order to remove the inner firebox. 45379: The Mid‑Hants Railway’s out‑of‑ticket ‘Black Five’ is the second steam locomotive to be based at Locomotive Storage Ltd’s facility in Margate, having arrived there by road on November 1. The Stanier 4‑6‑0 joins Jeremy Hosking’s ‘A4’ No. 4464 Bittern, which arrived there from Crewe in June (SR481).

32650: barely had ‘terrier’ 0‑6‑0t ‘sutton’ been re‑wheeled at the spa Valley railway (sr486) than its tanks were also fitted, as pictured in tunbridge Wells West shed on october 28. the tanks have been “almost completely rebuilt in‑house” and the overhaul of the stroudley engine’s boiler is to commence before the end of this year.

No. 45379 will remain there indefinite­ly while it awaits its turn in the overhaul queue at Ropley, and is not expected to enter the works until after BR ‘5MT’ No. 73096 is recommissi­oned (see SR485).

71000: New sets of Caprotti inlet and exhaust cams are to be produced for Duke of Gloucester, to the original 1954 design, reversing a modificati­on made during the last overhaul of the unique Riddles ‘Pacific’.

The three-cylinder ‘8P’ retains its original inlet cams in the centre cambox, but both outside cylinders and their camboxes were removed before the engine went to Barry scrapyard, and had to be made new in the engine’s first restoratio­n, completed in 1986. One of the original cylinders was sectioned for the Science Museum and can now be seen at Crewe Heritage Centre; the other was scrapped.

Trevor Tuckley, chairman of the BR Class 8 Steam Locomotive Trust, explains: “When the ‘Duke’ was rebuilt in 1986 it was decided that all the camboxes would be manufactur­ed to the original 1954 design. But during the 2004 overhaul it was decided to modify the exhaust cams to include a 15º retardatio­n.

“The reasons for this and the results obtained are not known. It has therefore been decided to manufactur­e completely new inlet and exhaust cams to the original 1954/1986 profiles, taking advantage of more modern machining methods, materials and heat treatment processes.”

The ‘Duke’s’ driving axle bearings are undergoing inspection at Tyseley Locomotive Works, and the tender tank will shortly be lifted off the frames for the overhaul of the running gear to commence. The main line electronic equipment (TPWS and OTMR) has been ordered and the electrical installati­ons on the tender are being designed, while gauging of the engine is also under way to ensure maximum route availabili­ty.

92134: The boiler of the unique surviving single-chimney ‘9F’ was lifted off the frames at the North Yorkshire Moors Railway on November 6 for final work, including fitting the superheate­r elements, superheate­r header, and the ashpan. The ‘Spaceship’ is a contender to be the next ex-Barry locomotive to return to steam after ‘Modified Hall’ No. 6989 Wightwick

Hall at the Buckingham­shire Railway Centre.

 ??  ??
 ?? ALAN JOHNSON ?? The overhauled frames, wheels and cab of ‘1366’ 0‑6‑0PT No. 1369 in Buckfastle­igh shed at the south Devon Railway.
ALAN JOHNSON The overhauled frames, wheels and cab of ‘1366’ 0‑6‑0PT No. 1369 in Buckfastle­igh shed at the south Devon Railway.
 ?? DAVE FULCHER‑INSULL ?? The boiler of ‘Large Prairie’ No. 4150 in the works at Bridgnorth on November 2.
DAVE FULCHER‑INSULL The boiler of ‘Large Prairie’ No. 4150 in the works at Bridgnorth on November 2.
 ?? RoBert faLConer ?? to mark the retirement of ‘Jinty’ no. 47324 at the end of its previous boiler certificat­e, an Lms‑themed event was held at the East Lancashire railway on november 22 2014, with the ‘3F’ 0‑6‑0t carrying its original number of 16407 and posed on shed at bury with ‘crab’ no. 13065. the ‘Jinty’ is expected to steam next year after a contract boiler overhaul, but the ‘crab’ will be out of action until 2020, when it will return with a new ‘ten‑year’ ticket.
RoBert faLConer to mark the retirement of ‘Jinty’ no. 47324 at the end of its previous boiler certificat­e, an Lms‑themed event was held at the East Lancashire railway on november 22 2014, with the ‘3F’ 0‑6‑0t carrying its original number of 16407 and posed on shed at bury with ‘crab’ no. 13065. the ‘Jinty’ is expected to steam next year after a contract boiler overhaul, but the ‘crab’ will be out of action until 2020, when it will return with a new ‘ten‑year’ ticket.
 ??  ??
 ?? TOM CLARKE ?? 75069: ‘Rebuilt Bridgnorth 2017’ reads the new worksplate on the front of the BR ‘4MT’ 4-6-0 in the Severn Valley Railway’s workshops. In fact, the major overhaul of the Riddles engine has run into 2018, but the end is now clearly in sight. When this picture was taken on November 4, fitting of pipework was well advanced with the double chimney and brake ejector due to follow.
TOM CLARKE 75069: ‘Rebuilt Bridgnorth 2017’ reads the new worksplate on the front of the BR ‘4MT’ 4-6-0 in the Severn Valley Railway’s workshops. In fact, the major overhaul of the Riddles engine has run into 2018, but the end is now clearly in sight. When this picture was taken on November 4, fitting of pipework was well advanced with the double chimney and brake ejector due to follow.
 ??  ??

Newspapers in English

Newspapers from United Kingdom