Beachy Head build timeline
2000: Project launched
2001: Tender chassis overhauled and lengthened
2004: Bogie platework delivered
2005: Driving and bogie wheels cast; main frames cut, joggled and delivered
2006: Atlantic House opened; original
Beachy Head regulator handle donated; tender chassis re-wheeled; Westinghouse pump obtained
2007: Main frames erected
2008: Cylinder and valve chest components delivered
2009: First motion parts cut; bogie frames assembled
2010: Valve chest assembly welded together; main axleboxes delivered; bogie and trailing wheelsets completed; cylinders fabricated
2011: Coupling and connecting rods machined and delivered; rear cylinder covers cast; axleboxes completed; smokebox saddle fabricated; cab reverser completed; valve heads cast
2012: Valve and cylinder liners fitted; frames supported on bogie and trailing truck; valve chest and cylinders fitted to the frames; covers fitted and pressure tested
2013: Main wheelsets completed and delivered; valve gear assembled; last major valve gear components delivered
2014: Reversing weighshaft and airclutch fitted; axleboxes metalled, machined and fitted; eccentric
rods fitted; most work between the frames completed; locomotive wheeled; cylinders clad; crossheads fitted; superheater header casting patterns completed
2015: Bogie and inside motion completed; running plates with splashers and steps completed; cylinder covers fitted; cab floor, sides and front assembled
2016: Connecting and coupling rods fitted; valves set; superheater header delivered; revision of internal boiler pipework completed; boiler work started; boiler tubes delivered; cab roof riveted together and fitted; mudhole patches welded into boiler; flue tubes delivered
2017: Smokebox door and surround completed; blastpipe installed; double Ramsbottom safety valves completed; reverser air valve, air-assisted reverser and clutch piped up and tested; ‘J’ pipe and main steam pipe installed in boiler and pressure tested
2018: Westinghouse pump and front footplating in place; boiler tubes installed and expanded; boiler repairs completed; tender work resumed; boiler moved outside and cladding sheets progressed
2019: Smokebox fitted and more boiler cladding made; tender pipework completed and timber to support tank fitted; cab floor and ashpan made; cab lined out; tender tank constructed and delivered; out of frames boiler hydraulic test passed
2022: First steaming?