Stirling Observer

Bridge work is forging ahead

Kerse Road update

- John Rowbotham

Network Rail say the ‘below ground work’ on the £6 million Kerse Road bridge reconstruc­tion has been completed.

Work is now underway on laying foundation­s for the bridge and building its abutments, the company explained in their latest update on the work’s progress.

Network Rail is replacing the Stirling Council-owned bridge – erected around 1968 – as part of the electrific­ation of the Stirling area rail network.

Kerse Road was reduced to one lane in January as preparator­y work on the 12-month bridge replacemen­t project got underway.

Full closure of Kerse Road was implemente­d on April 16 and the route will be shut until October 31 when it is due to reopen to two-way traffic.

Demolition of the bridge took place in April and since then work to prepare the ground for the new structure has continued.

A Network Rail spokesman said: “Over the course of the two demolition weekends, 100 members of staff and contractor­s clocked up more than 2,000 man hours to remove 10,000 tonnes of material from site.

“Since the demolition of the old structure, the team on site has been working hard and have successful­ly completed the piling works on schedule.

“This involved installing 88 piles to a depth of 29 metres using a 120-tonne piling rig and over 1800 tonnes of concrete.

“Now the below-ground works have been completed we are fully focused on constructi­ng the new bridge foundation­s and abutments. This will be progressed during June and July.”

The spokespers­on said the immediate focus has been on reinforcin­g newly-installed foundation­s using temporary steel structures.

Erection of scaffoldin­g and infilling areas up to the embankment is also underway.

Network Rail said surveys and other reports suggest the traffic management measures put in place in conjunctio­n with Stirling Council appeared to be “operating effectivel­y without any significan­t issues.

“We will continue to monitor this in conjunctio­n with Stirling Council as our works progress,” the spokespers­on added.

Although Kerse Road is closed to traffic, a temporary bridge is in place for walkers and cyclists.

To comment on this story: email john.rowbotham@ reachplc.com, or write to the Observer at 34 Upper Craigs, Stirling, FK82DW.

The team on site has been working hard and have successful­ly completed piling

 ??  ?? Going up Massive girders taken away during bridge demolition
Going up Massive girders taken away during bridge demolition
 ??  ?? Work in progress Constructi­on of foundation­s and bridge supports well underway
Work in progress Constructi­on of foundation­s and bridge supports well underway

Newspapers in English

Newspapers from United Kingdom