Stirling Observer

Beam me up

Importantp­haseunderw­ayinnewbri­dgebuild

- Robert Fairnie

A significan­t milestone in the constructi­on of the new Kerse Road Bridge will be reached this weekend.

Network Rail said the first beams of the new structure will be lifted into place using a 750-tonne crane.

For a week from tomorrow (Saturday) engineers will work for a combined total of 1800 hours as the first two pre-cast concrete beams, weighing between 30 and 50 tonnes and 21-metres in length, are lifted into position.

Iain McFarlane, route delivery director for the Stirling-DunblaneAl­loa (SDA) project, said the project was reaching a significan­t phase.

“Craning in the beams represents an important milestone as it is the first steps to reinstatin­g a bridge over the railway on Kerse Road,” he added.

“With the 14 beams in position, we will see the structure really taking shape as the new bridge emerges from the site.

“The beams going in is the latest in a series of critical steps towards reinstatin­g the bridge; including the successful demolition of the old bridge in April, the installati­on of 88-piled foundation­s and constructi­on of the new east and west abutments to support the new deck beams.

“I’d like to take this opportunit­y to again thank residents and the wider Stirling community for their continued patience as we complete this important element of the bridge reconstruc­tion.”

The Observer reported last month that the ‘below ground work’ on the £6 million reconstruc­tion project had been completed.

Network Rail is replacing the bridge, owned by Stirling Council and erected in 1968, as part of the electrific­ation of the rail network in the Stirling area.

The road was reduced to one lane in January as work on the 12-month replacemen­t project kicked off.

A full closure was then put in place in April and will remain until October 21 when the bridge is reopened to two-way traffic.

Network Rail say once the new bridge is complete there will be potential for the council to add a third lane to meet Stirling’s traffic needs and enhance the road network.

Electrific­ation of the rail network is being done to reduce journey times from Stirling to Glasgow and Edinburgh, increase capacity on peak services and provide longer, faster, greener trains.

 ??  ?? Progressin­g Picture taken yesterday (Thursday) as work moved towards critical phase
Progressin­g Picture taken yesterday (Thursday) as work moved towards critical phase
 ??  ?? Key element Beams will be lifted into position by 750-tonne crane
Key element Beams will be lifted into position by 750-tonne crane
 ??  ?? Bird’s eye view Work on the replacemen­t of Kerse Bridge
Bird’s eye view Work on the replacemen­t of Kerse Bridge

Newspapers in English

Newspapers from United Kingdom