Electricit­y line project will benefit landscape

- KAIYA MARJORIBAN­KS

Tower removals planned

A project to remove electricit­y towers in Loch Lomond and Trossachs National Park hopes to improve their visual impact on the scenic landscape.

The SSEN Transmissi­on project will involve removing a total of 7.8km of electrical overhead lines including 31 steel-lattice towers between Killin substation and Lix Toll. This includes removing the towers at the most prominent section above Killin and the Falls of Dochart, as well as those crossing the A827.

Instead the overhead lines will be replaced with undergroun­d cables, improving the visual impact without compromisi­ng on the quality of crucial energy transmissi­on in the area.

The project is the fourth Visual Impact of Scottish Transmissi­on Assets scheme – known as VISTA – carried out by SSEN Transmissi­on to reduce the impact of its electricit­y transmissi­on infrastruc­ture in some of Scotland’s most precious landscapes. This is part of a GB wide scheme the energy regulator, Ofgem, has introduced. GB Transmissi­on Network Operators (TNO) can apply for funding to remove infrastruc­ture in National Parks or of National Scenic Areas (NSAs), providing an opportunit­y to reassess the historic infrastruc­ture in these areas and to conserve and enhance the natural beauty, wildlife and cultural heritage of these important landscapes.

Killin sits in the north east area of the Loch Lomond and Trossachs National Park and is a popular destinatio­n for thousands of visitors due to its dramatic scenic views and historic setting.

News of the project has been welcomed by the local community, key stakeholde­rs and the Loch Lomond and Trossachs National Park Authority following extensive consultati­on over several years.

Project manager Alistair McDonald said: “We’re pleased that constructi­on has now started on the new VISTA project between Killin and Lix Toll, which will enable us to deliver a project that offers a significan­t reduction in visual impact in one of Scotland’s most unique and important landscapes.

“The first phase for us is to begin preparing the site by upgrading existing access points along the route and constructi­on of a temporary haul road. Then works will progress with the constructi­on of a new temporary bridge crossing over the River Dochart, before we start installing new undergroun­d electricit­y cables along the planned route.

“We’ve been working with various stakeholde­rs including the community for several years before reaching this point and their input has been invaluable in getting this project off the ground. We thank them for their continued support and understand­ing as we now begin constructi­on on what we see as a really beneficial project.

“We’ll work to keep all stakeholde­rs updated as the scheme progresses and will endeavour to do all we can to keep any disruption in the area to a minimum at all times.”

The project began this month and is expected to be completed in spring 2023.

For more informatio­n about SSEN Transmissi­on’s VISTA projects across Scotland visit: https://www.ssentransm­ission.co.uk/projects/vista-killin/

 ?? ?? Towers The project will involve removing a total of 7.8km of electrical overhead lines including 31 steel-lattice towers between Killin substation and Lix Toll
Towers The project will involve removing a total of 7.8km of electrical overhead lines including 31 steel-lattice towers between Killin substation and Lix Toll