Sunderland Echo

Asbestos delays centre work

£2MILLION LEISURE CENTRE REVAMP HELD UP FOR MONTHS

- By Fiona Thompson fiona.thompson@jpress.co.uk Twitter: @fionathomp­sonjp

Asbestos removal from a leisure centre’s roof has pushed back the completion date of a £2million-plus redevelopm­ent by months.

Work at Peterlee Leisure Centre had been due to be finished by the autumn of this year, but is now expected to come to a close by next spring.

Durham County Council had said in March that the project was on schedule, with the completion date pushed back after it discovered the task of removing asbestos found in the building’s roof would be greater than first thought.

The roof maintenanc­e at the leisure centre was already part of the work when the issues involving he asbestos were establishe­d.

The council has said the need to remove the materials will not add to the cost of the work.

The revamp work includes refurbishi­ng its changing rooms and creating a new reception, with the swimming pool to reopen to visitors following a period from September to January when it closed while demolition work was carried out at the front of the building and while temporary changing areas were set up.

A new sauna is also being installed within the pool complex after calls from customers left angry when the old one was to be scrapped from elsewhere in the building.

The redevelopm­ent also involves moving the library into the St Cuthbert’s Way site after the old reference and lending service in Esssington Way was knocked down as it was connected to the former East Durham College campus.

The land has been cleared by Tesco – which made a deal with the council over the library site – as it looks to market the plot to a new owner after it decided to axe plans for a new superstore.

A temporary library has been opened at the leisure centre in the meantime.

Su Lewis, projects and transition­s manager at the council, said: “While carrying out the work at Peterlee Leisure Centre, we discovered the extent of asbestos removal was greater than originally expected and this has led to the planned completion date being pushed back. This unavoidabl­e delay means all work is expected to be finished by spring 2019.

“However, in the meantime, the pool will remain in operation albeit on a limited basis and all other services will remain open to the public as usual. Since the temporary library opened in December the facility has been well used. Throughout January, over 8,000 books were issued, and public access computer usage has remained high.”

 ??  ?? Peterlee Leisure Centre pictured before the work began.
Peterlee Leisure Centre pictured before the work began.

Newspapers in English

Newspapers from United Kingdom