The Arran Banner

Final work start as access system arrives

-

The work to complete the new £22 million Brodick ferry terminal is finally under way after the arrival of the passenger access system (PAS).

The project, which was due to be completed at the end of August, was delayed owing to Spanish manufactur­er Adelte not completing the constructi­on of the movable access system on time. It is its largest single section PAS built to date.

However, Monday saw the first of three sections arriving at the pier where two large cranes were awaiting them, which had arrived by barge over the weekend.

The installati­on and commission­ing of the three large sections will take around six weeks to complete with the terminal expected to open by the end of October or the beginning of November. The building work by contractor George Leslie Ltd has the company complete the terminal redevelopm­ent on budget and in line with the revised timetable and it is currently completing final testing and commission­ing of the buildings services.

CalMac, meanwhile, is busy with the fit-out of the building in preparatio­n for the completion of the new PAS. Once all of the systems are complete and the PAS has passed all of the operationa­l checks, CalMac will begin operating from the new facility.

Head of civil engineerin­g at CMAL Ramsay Muirhead said: ‘We are pleased that Adelte has now completed manufactur­e of the new PAS and its delivery will see the final phase of the project underway, and the opening of the facilities soon after completion.

‘We are continuing to work closely with Adelte to ensure the work is completed as efficientl­y as possible.’

 ?? 01_B36CMAL02 ?? Workmen direct the lorry with the first of three sections required to complete the remaining passenger access system.
01_B36CMAL02 Workmen direct the lorry with the first of three sections required to complete the remaining passenger access system.

Newspapers in English

Newspapers from United Kingdom