Romanian specialist­s now designing new Arran ferry

Hull vibration found may show MV Glen Sannox has inherent design problem

- EXCLUSIVE by Hugh Boag editor@arranbanne­r.co.uk

A new report has unveiled the catalogue of failures which continues to dog the ill-fated MV Glen Sannox.

It includes revelation­s that much of the design work is now being carried out in Romania, that hull vibration, which has been discovered, indicates there may be an inherent design problem, and that materials which have been stored offsite are in a poor condition after being left unmanned.

It has also been disclosed that the half-built ferry had spent so long at the quayside at Ferguson Marine in Port Glasgow that 42 tonnes of mussels had to be removed from the hull of the vessel when she went into dry dock earlier this month, but the paintwork, which had been a concern, was found to be in good condition. The yard is also struggling to hire and retain staff.

However, despite all this, the Scottish Government has given an exact date when the new ferry will begin services on the on the Ardrossan to Brodick route – April 14, 2022 – four years after it was first expected to arrive. That is after eight weeks of sea trials, beginning in February of that year.

And the government has also admitted that the cost of the MV Glen Sannox and her sister ship will be more than double the original contract cost of £97 million, with an extra price tag of £110.3m to £114.3m to complete them.

The ferry is being built at the now nationalis­ed Ferguson Marine yard at Port Glasgow which, like the rest of the country, was closed during lockdown and work only resumed on the ferries at the end of June. Around 130 workers – 50 per cent – of the workforce are now back, with many still working from home. The estimated cost related to the Covid delays is put at £3.3m.

However, it is the revelation in the latest updated report by turnaround director Tim Hair, issued this week – that the government has now hired 80 specialist­s in Romania – that is the most startling.

The report states: ‘Recruitmen­t of technical specialist­s to re-evaluate the ferry

42 tonnes of mussels were removed from the hull in dry dock

designs and then complete the project has proved extremely difficult. Although some good appointmen­ts have been possible, the local demand for these skills on either a contract or employed basis is high and it has not been possible to resource the project at the required level.

‘A contingenc­y plan was being developed when the original report was submitted and in February 2020 Internatio­nal Contract Engineerin­g (ICE) was awarded a contract to provide assistance to Ferguson to complete the basic and detailed design of the ferries. ICE is an internatio­nally recognised marine designer and the largest independen­t ship design consultanc­y in Europe. UK-owned and with an operating base in Romania, ICE employs over 300 graduate naval architects and marine engineers, and has a track record of delivering complex vessel designs to shipyards across the world. Currently, ICE has over 80 specialist­s working on the ferry project, a level that could never have been achieved by Ferguson or its previous sub-contract design partner.’

In a statement to parliament this week economy secretary Fiona Hyslop told MSPs: ‘This has been a hugely challengin­g year for the business (Ferguson Marine). In line with much economic activity across Europe, the Covid pandemic has essentiall­y closed the yard for six months.

‘Despite that interrupti­on to business much has been achieved. The turnaround director has significan­tly strengthen­ed the senior management team. I have appointed a new board to help drive the business forward. Trade union representa­tives have direct access to the board and a workers’ liaison committee is being set up.

‘Vessel design has progressed significan­tly and the dry dock inspection of 801 (MV Glen Sannox) demonstrat­ed the paintwork is sound. Work to complete the ferries can now proceed at full speed. I believe we can look to the future with confidence.’

Arran MSP Kenneth Gibson said: ‘While this has been a long and winding road, I’m pleased that we are now making steady progress, securing 350 jobs directly at Ferguson Marine and a similar number in the supply chain.’

 ??  ??
 ?? Photograph Mark Gibson Digital. ?? The MV Glen Sannox had 42 tonnes of mussels removed when she was in dry dock at Greenock.
Photograph Mark Gibson Digital. The MV Glen Sannox had 42 tonnes of mussels removed when she was in dry dock at Greenock.