Tunnel refurb could drag on into 2021

NEW LIFTS YET TO BE FITTED

- Daniel.holland@trinitymir­ror.com @DanHolland­News

LONG-OVERDUE works to finally complete a renovation of the Tyne Pedestrian Tunnel could drag on for more than a year after it reopened.

The crossing finally opened to the public last August, years later than had been promised and millions of pounds over budget.

But new inclined lifts still needed to be installed and, after a string of delays with an Italian contractor, that work has now been pushed back even further because of the coronaviru­s pandemic.

The firm building the glass lifts is based in the Lombardy region, which has been at the centre of the Covid-19 epidemic in Italy, and its staff are not expected to be able to return to complete the tunnel works until September at the earliest.

Tyne and Wear councillor­s were told on Thursday afternoon that the return date was far from certain and entirely dependent on European travel restrictio­ns to control the spread of the virus.

After the tunnel, which connects Howdon and Jarrow, was reopened last August it was said that the lift work should have been completed the following month, before the completion was pushed back to

December – a target date that was also missed.

A report to the North East Joint Transport Committee reveals that a visit from Maspero Elevatori workers in January failed to take place.

It adds: “Extensive dialogue has taken place to try and resolve the outstandin­g technical issues preventing the lifts for being completed, certified and brought into service.

“However, the return of the contractor to site is currently on hold. The contractor is based in the Lombardy region of northern Italy and at this time the area remains in ‘lockdown’ as a result of the Covid-19 outbreak.

“Travel restrictio­ns are in place which means that contract staff cannot travel to the UK. Until they can return to site to complete the outstandin­g works, testing and certificat­ion for use, they cannot be brought into service.”

Work to refurbish the Grade-II listed structure should have been completed in 2015, but was plagued by a string of problems including the discovery of asbestos and its main contractor going bust.

The cost of the project also spiralled from £6.9 million to more than £16 million.

The pedestrian and cycle tunnels have remained open during lockdown with social distancing measures in place so that users can follow and one-way system for travelling in and out at either end and to ensure that the existing vertical lift is only used by one person at a time.