Fife offshore windfarm overcomes first hurdle

ELECTRICIT­Y: Neart na Gaoithe array gets power contract back, but challenges remain

- Graham huband business Editor ghuband@thecourier.co.uk

A planned £2 billion windfarm off the coast of Fife has overcome one major hurdle to its developmen­t.

The 450MW Neart na Gaoithe (NnG) array – which is planned to be built on a site 15km off Fife ness – is one of the largest energy infrastruc­ture projects being pursued in Scotland.

It has the potential to create enough power to supply more than 325,000 homes, but has been left hanging in the balance after a double blow.

The project was first caught up in a court challenge by nature lovers.

It then had its vital power contract rescinded.

Neart’s Contract for Difference (CfD) was awarded by the Low Carbon Contracts Company (LCCC) in March 2015 following a competitiv­e tender process.

The agreement – one of just two handed out at the time – entitled NNG to an inflation-linked strike price for the electricit­y it produced over a period of 15 years.

LCCC’s decision last March to remove NnG’s contract – which was initially awarded at a strike price of £114.39 per megawatt hour – was seen as a potentiall­y lethal blow to the project.

However, Dublin-based developer Mainstream Renewable Power challenged the decision, and the CfD has been reinstated following a tribunal.

“LCCC and NnG submitted a dispute relating to the terminatio­n of NnG’s CfD to arbitratio­n,” the companies said in a joint statement.

“The arbitral tribunal has made its decision in NnG’s favour under the dispute resolution procedure set out in the CfD.

“The details of the dispute are, and will remain, confidenti­al as both parties are bound by the confidenti­ality obligation­s both within the CfD and the rules of the arbitratio­n.”

While the decision is positive news for Neart, the project and two other multibilli­on-pound schemes – Inch Cape and Seagreen – being pursued for waters off Fife and Angus remain on hold.

The developmen­ts cannot begin until the outcome of an appeal is clear into the Court of Session’s ruling that consents provided by the Scottish Government for the arrays were seriously flawed in both procedure and substance.

The case was brought against Scottish Ministers by the bird preservati­on charity RSPB Scotland after they sought judicial review of the planning approval decisions.

Scottish Government, Mainstrean and Inch Cape brought forward appeals in August, and a further ruling is expected within months.

 ??  ?? Turbines installed as part of SSE’s Beatrice demonstrat­or project. Perth-based SSE is a co-venturer on the Seagreen windfarm project which is stalled by a court challenge.
Turbines installed as part of SSE’s Beatrice demonstrat­or project. Perth-based SSE is a co-venturer on the Seagreen windfarm project which is stalled by a court challenge.