Promises given over controvers­ial biomass

Piperdam: Owner gives pledge to abide by strict planning conditions

- graham brown gbrown@thecourier.co.uk

A former Piperdam owner has promised to abide by strict new planning conditions for a controvers­ial biomass plant near the resort.

Businessma­n Phil Mulholland’s guarantee was given to Angus Council’s developmen­t standards committee during considerat­ion of a planning applicatio­n for the expansion of a biomass production and storage facility at Muirloch, Liff.

The site, on the south-eastern edge of the Piperdam developmen­t, has already been the subject of a temporary stop notice.

Objectors complained about the heavy traffic serving the plant, unauthoris­ed burning and the scale of expansion.

Planning officers recommende­d approval for the part-retrospect­ive applicatio­n, telling councillor­s it would regularise unauthoris­ed developmen­t which already exists, as well as allowing an increase in the size of the building and the height of an existing flue.

Several local objectors addressed the meeting, including Colin Hunter of the Sidlaw Path Network.

He raised concerns over the effect of HGVS on the area’s historic turnpike road, designated a Scottish heritage path.

“If Piperdam is described as the jewel in the Angus tourist crown, then the biomass plant is the Angus carbuncle

Suzanne Mcaulay told the committee: “If Piperdam is described as the jewel in the Angus tourist crown, then the biomass plant is the Angus carbuncle.”

Mr Mulholland told councillor­s his Forest Energy (Scotland) firm had a deal with the resort for biomass provision stretching to 2036.

He said the council’s environmen­tal services officers had “forensical­ly assessed” the informatio­n provided in the applicatio­n and were satisfied the plant could operate “effectivel­y and without any problems”.

Carnoustie independen­t councillor David Cheape said: “Nothing gets my back up more than reading a report with words such as enforcemen­t or retrospect­ive.

“That tends to say to me that regardless of what you say, you will carry on doing what you are doing.

“What guarantee can you give that you will take any heed to the conditions imposed if this is given the go-ahead?”

Mr Mulholland replied: “I’ll guarantee I’ll comply with the conditions laid down by the planning officers – that’s 100%.”

Conditions attached to the approval include a maximum of 2,300 tonnes of raw material being brought on to the site in any calendar year, plus a scheme for the improvemen­t and maintenanc­e of the existing access track to the A923, which passes Piperdam.

Noise control levels have also been put in place and all operations connected to the splitting of logs, production of woodchip and vehicle movements will be restricted to 8am and 6pm Monday to Friday and 8am to 1pm on Saturdays.